Porur flyover status

Q: Hello all..what is the status of Porur flyover. Has the construction resumed..?
Reply

Replies (5)
1
Hi Abhishek. Porur flyover was put on hold due to delay in shifting of the water mains from the Chembarambakkam lake that run beneath the road’s surface. And also some land issues.
Ramana Vignesh


2
I think the construction was initiated in 2012 only and by June..it got stuck..only 20 percent work is completed. Lets see will the construction start in next six months.
Lekshmi


3
Hi all..i am new to Chennai.. and live near Porur. I see this flyover every day...can you tell why the construction got hold..??
Abhishek


4
Good to hear that ..Highways department is taking some effort. This flyover was decided to costrcut to ease traffic flow. Ans delayed construction is increasing traffic.
Lekshmi


5
The construction is likely to resume in October 2013. Highways department has decided to do all work on its own.
Ramana Vignesh