Due to the delay of the project the connectivity between Delhi and noida is in tassels,

Q: Due to the delay of the project the connectivity between Delhi and noida is in tassel, so kindly let us know when the project is going to end?
Reply

Replies (13)
1
Yes the price appreciation is likely to witness a steep hike among these sectors in future.
Amit Raj


2
The real estate with in this sector will boost up with no time
Subhaduti Mahankar


3
So will the price of the project will go up?
Raj Purohit


4
Yes and this are the sectors which will have the benefir Jaypee Aman is Sector 153, then a thin road goes onto various sectors
via villages etc 155, 156, 158, 159, Villages, 161, 166, 167, Villages,
to 168.
Meha


5
This new bypass will smoothen the heavy traffic moving to and fro from Noida to Delhi. This bypass will connect the developed sectors on both sides of e-way at Mahamaya flyover.
Shabnam


6
I think this bridge will also improve the real estate in Noida
Ramneek


7
Kalindi Kunj road will be a benefit for the residents staying at sector 35 Noida and beyond this sector.
Kunal


8
The project was supposed to start in May 15, 2003 and was expect to be completed by May 14, 2005.
Kaushik Bardia


Gurmeet
How will it effect the real estate in both the place?
24th July 2013


9
But guys i heard that last year the court revised the order and allowed road to be built 120 m
away from the river. Although UP government refused to give away land
in and around the bird sanctuary and sand mound near the Yamuna,
bringing the project to a halt
Balwinder Singh


10
The Delhi High Court in 2006 passed an order prohibiting road construction within 300 metres from the edge of the river.
Harmeet Kaur


11
2003 the bridge was approved then what took the delay?
Joydeep D


12
The Government sanctioned the 6.5-km bypass from Kalindi Kunj Colony Ring Road to Kalindi Kunj Road in March 2003 at a price of Rs 63.41 crore.
Vasanth


Wont the delay of project increase the budget?
24th July 2013


13
The bypass will be an additional road between Delhi and Faridabad which will cover the 13.2KM distance between DND flyover (Delhi side) and Kailgaon village along the Yamuna bank.
Jeet Bhaskar


This will end completed with this year...till then we have to bear this
Praveen P,  Delhi
24th July 2013


What is the budget the govt has approved for this?
Nikhil Agarwal,  Delhi
24th July 2013