Continuation from my previous post - Following are some of the grievance points that we have given them in writing –
1) The original handover date was in June 2010. Now the 6 month grace period is also over and further 2.5 months have passed – still there is no semblance of completion or handover
2) No formal communication from Doshi on reasons for the delay. Also the site supervisor / customer executive are not giving any clear picture on the plan for house handover
3) Many of us have taken housing loans and are paying huge EMIs – so every month’s delay is costing us financially
4) Many owners have finalized children’s education in Tambaram based schools based on original handover date. Now because of the delay they are not able to decide the admission, especially since the admission year will be starting
Dear owners – I would request all of you to provide any further grievance points to the above list so that we can present a strong case during the meeting with Dos
Hi all – My name is Sashi Kiran – I am one of the Doshi Nakshatra 1 owners
This is just to update all of you that 4 of us (Mr Sigamani, Commander Ganeshan’s father, Mr Xavier and myself) had visited Doshi’s office at Kilpauk this Saturday (March 19th) to inquire into the reasons for the delay in the completion and handover of the project. Though we could not meet anyone in the Top Management, we met Mr Muthukumar (from Admin Dept. Contact no.- 9282333428) and Mrs Filomina (Sales Manager). We presented some of our grievances in writing to them and Mr Muthukumar has assured us that he would arrange a meeting with the Director or someone else in the Doshi top mgmt (most probably on the coming Sunday – actual date to be told to us)
Following are some of the grievance points that we have given them in writing –
1) The original handover date was in June 2010. Now the 6 month grace period is also over and further 2.5 months have passed – still there is no semblance of comp
Gentlemen, i am also one of the proud owner of doshi nakshatra I project. My contact no.09820943685 and email id ganzio72@hotmail.com. Can we be in touch please !
Hi All,
I have booked the flat in Swathi, and now they are not even allowing to woodwork in the apratment, and there answer for allour queires is " we will let you know", But again that too dont have any deadline. How can an experienced builder in this field cant predict the problems at finishing stage. They also state that they are waiting for CC. My suggestion is we all (except those who are in abroad should meet at site and discuss with Doshi management for the completion of the project.
If any one is interested on the same please contact me on 9486283160
Regards
Xavier
hi srini,
i have paid upto 85%.some transformers are fixed inside nak-I and TNEB main boxes are inside . i dont why they are making late???.can you ask any other owner from nak-I and check him out directly to main office.
Hi Selva.. Thanks for the update.. I had a word with the Doshi guys over the phone and was told to believe that they have stopped the work and even further bookings since the electricity connection was still pending. As usual they did not give any idea on the final date of completion. I do not think there is any clause in the agreement which can pin them down.... Can you clarify up to what level of payment have you made? Regards Srinivasan
Hi all - I also feel that we should meet at a common time at the site to discuss the progress. Also, it is now almost 15 days past the due handover date and there is no communication on the delay from Doshi's side. It seems we need to take a hard stance on this. What do you all say ?
I am right now out of the country on a business assignment.. I am getting mails from Doshi asking for the 95% payment.. Not too sure if they are progressing at all.. Can any of you give me an idea on the status of construction now and if you have paid the 95% payment already?
I am Sashi Kiran, I have booked a flat in Swathi Block. Nice to get to know people.
By the I understand that DOshi were supposed to handover the completed house by 31st Dec'10. That time has elapsed, however the work is still in progress.
I guess they are supposed to pay a compensation on any delay post Dec 31st so we should be asking them for the compensation now. Your opinions please.