Q:I want to buy a three or two bedroom flat in Doshi Nakshatra east or north facing either in first floor or in second floor. Will you be able to send the details at the earliest?
Q:We should specifically ask Doshi top management with regard to delay in getting power connection,sofar no action initiated for drainage,reason for stopping further booking(nobody will dare to stop booking at this level as they had invested lotand market is also stable)and then we owners to meet at a common point and time.SIGAMANI
Q:Hi, if any of the owner from Doshi Nakshatra I is willing to sell their apartment on a resale basis, please contact me. Requirement would be 2BHK with the maximum SFT, preferably Bharani Building.
Latest Answer: Continuation from my previous post - Following are some of the grievance points that we have given them in writing –
1) The original handover date was in June 2010. Now the 6 month grace period is also over and further 2.5 months have passed – still there is no semblance of completion or handover
2) No formal communication from Doshi on reasons for the delay. Also the site supervisor / customer executive are not giving any clear picture on the plan for house handover
3) Many of us have taken housing loans and are paying huge EMIs – so every month’s delay is costing us financially
4) Many owners have finalized children’s education in Tambaram based schools based on original handover date. Now because of the delay they are not able to decide the admission, especially since the admission year will be starting
Dear owners – I would request all of you to provide any further grievance points to the above list so that we can present a strong case during the meeting with Dos