can we all not meet and go there together and find our answers ?
Q: i can seee tht all of us are facing the same problems even i was made to change my flat and evrything very troublesome plus the work is not starting i think we all shud go there together
Yes, I have also booked 2bhk in 2011 that time their site representative have promised that you will get the position in the end of 2013, but if we see the progress of the work is still not yet started properly I have visited this site in last month while asuming that its take another 2 to 3 years to complete the entire complex, lets meet and connet each one who has booked in this project and we will come together and push the builder , If we did not take any action know the we have to suffer, we are end user not a investor if we quit also then we cannot get at the same rate so lets push togther to builder and get the final commited date or we will ask them to pay some monthly rent till the time they complete this project
Ashok true they r not doin ny work i also calld n tht sunil shouts nd tlks to me as if ehsaan kar rahe hai .lets tlk this out got ur number shall buzz u abt the problem
Hi friends, you can know more by clicking on Man Opus, Mira Road and then there is a tab "Join Owners Group". You can click on the tab and provide your contact details to be approved by the admin. After that you can contact with other residents for further details about the project and share your views..
Abhishek, I had booked a flat in this project and I was told that the construction work will be done by March 2014.. But still there is not much progress at the site. It is like wasting our hard earned money on something which is not ours..
Hi Anisha, even I had booked an unit at MAN OPUS on April 2011. Their people told that the project will be completed by end of 2013.. But seeing the pace, I don't think it will ever get completed.. What a waste! Few days back, I had called their head office and they are still saying project will be ready by the time commited.