Any news on the Chengapalli- Neelambur Road Widening Project?
Q: Hey what happened to the six-lane road widening project between Chengapalli to Neelambur. Wasn't it suppose to be completed by like 2012? I haven’t heard a thing about it.
This isn't the only project facing delay, there are five more. Anyways, I hear that they are going to have some meeting soon with the State Government and the contractor, so they will hopefully fund this project’s shortcomings, and we will have a good widened road.
So, they've completed like 75% of the work, the problem is with the rest of the 25% work. It’s just dead stuck. I read in the news that they need around 260 crores rupees to finish this. So, till that 260 crore is sanctioned, it’ll not get completed.
Well, those dates hold good only for papers. The construction is still on, and it’s going on at a very very slow speed. It started in 2010, but they have a lot of regular financing problems, hence, it is taking forever.