I'm shocked to hear all this. We are still in talks with the builder. We are asked to pay 5.5 laks. What is the progress of the case?? I don't live in India so it's very difficult for me to initiate anything. But would like to know if there is a positve outcome.
This is Jennifer, we are in the same boat. The builder is charging us interest and refusing to hand over the apartment What was the outcome of your discussion with the builder. We live abroad and find it difficult to handle this.
Hi Vidhya, The builder (Lalitha Devi is the CRM) is sending me notice to pay an interest of Rs. 50 thousand rupees. I booked the flat in 2010 and at that time they promised that they have approval for 11 floors and extra 7 floors will be obtained in a short while. It was promised orally that the estimated time of completion was June 2013. Then in the agreement they mentioned that the time frame will be 2 years from getting approvals. We have been kept blind on their approval process. My money is with them for more than 4 years. Will Alliance pay interest for that? If anybody going to consumer court let me know.
We are going through similar issues and would like to understand the progress if any ........ Are there any email ids or numbers of the senior management team that customers can contact . ?
Hi vandana, there is no means to talk with the builder , in agreement paper builder mention his point of contract clearly so it better to take legal exper with all your document available with you he will better suggest some point in this matter.
This is day light robbery. They are en-cashing the helpless situation of the buyer. When they sent the statement earlier this interest was not mentioned. When we put pressure for hand over, they have come out with this. This may be their strategy to prevent anyone from asking for the compensation for the delay. Defense in the form of offense. Where they will take all these money to?
Hi Vidya, I am just getting into the similar issue with the builder and he is demanding 6 Lakhs as interest. What was the outcome of your issue? Appreciate your response. Regards MS
Hi Vidya , I am in same page like Allience is extra amount Rs 1.8L as interest part as you know all payments done by LIC based on physical progress of construction , I am filling case if your interested lets know , You can call my wife her number -9941242844
Hi Chand Any progress on your issue. Please let me knw, My flat roof is leaking, when we approach they said this leakage is bcoz of top floor washing machine.
First you discuss with the builder regarding this issue. If this same thing is happening with your neighbors ,then discuss with each other. Discuss with other flat owners & consult with a local advocate. Or else you can send a legal notice to builder asking for deficiency of services.