The work is on a complete stall, any updates when they are going to commence the work..

Replies (111)
1
Admin of the whatsapp group kindly add me up no 919892222266
Tanveer Shaikh


Hi,
Yes, it is a long delay project and still there is no sign of construction. Did you talk to to the builder recently? What are they saying? You alone can not do anything so form a group and pressurized the builders.
10th December 2015


2
How can one contact Deepak Trivedi, any email add or contact no would be helpful
Tanveer Shaikh


Deepak Trivedi - 9820723508
30th November 2015


3
The work on the project is at a complete standstill. The flat/shop purchasers have formed an association the Meadows Owners Welfare Association to interact with the builder and take necessary steps for welfare of the flat/shop purchasers. All flat / shop purchasers are requested to contact Deepak Trivedi and become members of the association. A united front will be helpful against the builder.
Ramesh gajria


Hi,
You can join the Commonfloor Group, of HDIL The Meadows, Goregaon West, Mumbai by clicking on this link https://www.commonfloor.com/hdil-the-meadows-mumbai/covp-8joa1j and http://groups.commonfloor.com/ and get in touch with other owners who have already booked a flat in this project and discuss about the same.
Commonfloor.com's apartment management software is absolutely free of cost, Anti spam and provides complete data security and privacy(http://www.commonfloor.com/apartment-communities/pricing).
To find the benefits of joining the software please find this link ( http://www.commonfloor.com/apartment-communities/benefits-owners)
Already 1 lakh apartment society are using Commonfloor Groups to bridge the gap of communication among the owners and MC ( Management Committee)

(http://businesswireindia.com/news/news-details/commonfloorcom-launches-commonfloor-groups/38909 )
Sanjana Jain,  Mumbai
20th October 2015


Hi Ramesh,
You can not blame a builder every time. If he is not getting the approval then how can they start the work. May be your builder is facing the same problem. Nobody want to lose their reputation.

You might have heard Suraj Parmar's death, a prominent builder in Thane who ended his life due to the repeated demands for bribes by the several government departments. They are also the victim of the and the the way the system works.
Ashish Sharma,  Mumbai
30th October 2015


Right Ashish,
The approval process has become indescribable lengthy, tedious, unpredictable and depends on the whims of individual officers. Getting approvals has become a major problem for builders and has increased the interest cost not just of the builders but also of consumers.

Because of that Maharashtra Govt. has to take few necessary steps against the approval process. You might aware of that.
Rajatrawal,  Mumbai
30th October 2015


Hi i am also one of the buyer in the same project , please let me know if we have any whatapp group ?
I would like to be part of the same.
Mukesh,  Mumbai
17th May 2019


4
@Deepankar,
As far as project connectivity is concerned Goregaon West is located within close proximity to the proposed Goregaon-Mulund Link Road that will serve as a link between the Western and Eastern Express Highways. Motilal Nagar - 1 Km), Oshiwara - 2 Km, Chincholi Bunder - 2 Km, Malad West - 2 Km and Lokhandwala - 2 Km are some of the localities near this area.
Praveen Modi


5
HI,
Goregaon West is one of the suburbs of Mumbai located in the Konkan region and is about 11 kilometers from the city of Mumbai. It enjoys great connectivity with the Western railway line on one side and the Western Express Highway and Link Road on the other. Udyog Nagar - 6.8 km, Unnat Nagar - 7.3km, Kumud Nagar - 8.4 km, Milat Nagar - 9.5 Km and Best Nagar - 9.6 km are some of the famous localities of Goregaon West.
Deepankar Godbole


6
HI everybody,
HDIL Meadows is a very good project and builder the builder is also one of the reputed builder in the industry. The project is expected to get completed by mid of 2016.

Goregaon has very good road infrastructure and is well connected to other parts of Mumbai. The suburb has the Western Express Highway and Link Road passing through it. The Mumbai International Airport is about 14 km from Goregaon and can be accessed via the Western Express Highway. There is currently no metro station here. However there is a metro station proposed in the Shastri Nagar locality during Phase-III construction of Metro.
Praveen Modi


7
Hi all,
HDIL is now charging for flower beds, dry balcony etc and have increased the size of each flat by30% and are asking for rs 12000/sq-ft for the same. Average increase is 35L for 2 BHK to 75 L for 4 BHK. To arm twist buyers HDIL has enforced force majeure to stop work siting non availability of sand. As their chairman told buyers recently and i quote " you can go to court you will not get your house for the next 10 years".
Ramesk Polekar


Hi all,
It is better to ask the builder face to face. Don't follow any rumors. The discussion made on it may be for harassing the builder or may be the customers own view. DLF is a brand name and i hope they will not do such small mistakes in their project.
Praveen Modi,  Mumbai
20th November 2014


8
Hi All,
After reading all above comment can anyone suggest whether I should go ahead investing in the project?
Abhay
Abhay G


Hi Abhay,
It is come to know that the builder is in poor financial condition. I have also invested in their project. I am worry about my hard earned money.

It is also come to know that they have issued a notice to all buyers of Metropolis and force majeure clauses in the agreement and have stopped work on the project siting lack of sand availability.
4th July 2014


Hi Vineet,
Hey, it seems to me that it is twisting move to extract more money from buyers in the project who have valid registered agreements and also to mask the fact that they have illegally completed construction on 4 extra floors for which they have no CC.
Praveen Modi,  Mumbai
4th July 2014


9
You can join the owner's group, of ( HDIL The Meadows) ( Mumbai) by clicking on this link ( http://www.commonfloor.com/forum/4ebd73eb179ec-a) and get in touch with other owners who have already booked a flat in this project and discuss about the same.

Commonfloor.com's apartment management software is absolutely free of coast, Anti spam and provides complete data security and privacy(http://www.commonfloor.com/apartment-communities/pricing).

To find the benefits of joining the software please find this link (http://www.commonfloor.com/apartment-communities/benefits-owners)
Sanjana Jain


I am owner of flat c-1004 in hdil meadows. Please include me in the group. VS Chadha 9820531147
uyt ewr, Apartment Resident 
23rd June 2014


10
Kindly add me to the Whatapp group.

Bimal Kumar Lal
Mob- 8806667730
bimallalin@yahoo.com
Flat No. C-703 -Meadows
Bimal Kumar


Dear ALL please add me to the HDIL Meadows group, i have booked in A wing 25th floor, invested all the efforts and GOD knows where the HDIL will take us, please join me on watsup 00971558795421, I am presently in UAE. thanks
Abdul Razzak,  Mumbai
8th July 2014


11
Request all who have booked flat in HDIL Meadows, Goregaon project to please get in touch with Mr. Deepak Trivedi who will add you in whatsapp. Below is his details - dear all, kindly provide your mobile nos and name and email address, we also have whats app group, will add you to whats app, regards deepak / 9820723508 / -
Nisha


Pl add me in whats up 9820011537 And 9820013537
Blagarwal, Apartment Resident 
18th March 2014


Pls add me 09821208650
Abdul Razzak,  Mumbai
26th July 2014


Hi ,
I have booked a flat in HDIL Meadows ,its almost 3yrs and there is no development of the project .Can anybody tell me whats happening ?.....Mrs.Rao (9819455132)
pranitha rao ,  Mumbai
2nd August 2014


Please add me in whatsapp on +97455673147. This is my Qatar number. I booked a flat in meadows during the bhumi Pooja on June 2010 and I was told I will get the possession by dec 2013. I don't see any sign of completion.
Akash,  Mumbai
6th October 2014


12
Let everybody be part of the group active on whats App. please contact or send direct message to +91 98 33 88 4273 and keep yourself updated
hira


13
can you please add my email in your group priyag74@gmail.com I have booked flat in medows HDIL goregaon west
Piya G


14
can you please add my email in your group priyag74@gmail.com I have booked flat in medows HDIL goregaon west
Piya G


15
dear all , i also have an apartment in meadows G wing , apparently this wing has not even reached plinth level , , kindly add me to your group my email id is kapilbhatia22@hotmail.com
kapil bhatia


16
Nothing concrete. They said that because some other project was nearing completion all their workforce was deployed there. Meadows work will start after Jan/feb 2014. HDFC bank was approving the project for loans. Will send you detailed email on it if you share your email id.
Ramesh gajria


17
Please share the minutes of the meeting for the benefit of members away from Mumbai.
hira


18
We had a meeting with HDIL representatives today. About 20-25 persons attended. Hope next time we have a bigger turnout.
Ramesh gajria


dear Mr. Ramesh, when will you be having the next meeting, please let me know, appreciate, thanks
Abdul Razzak,  Mumbai
10th July 2014


19
We are ready to wait till 2016 also
hira


20
Just registered my agreement last week. There were 4-5 others also who were getting their agreement registered on the same day. There was also a newspaper advt. last week which mentions Meadows possession in Oct 2016 while the agreement states Aug. 2015. So don't expect possession till 2016-17.
- Ramesh 9821039269
Ramesh gajria


21
A wing Flat 1002 / Mobile 00971 55 9724368 /ken /ken_g710@hotmail.com Please add me to this group
Ken


22
also kindly provide your wing / flat no / mobile nos / name / email address, we also have whats app group, will add you to whats app, regards deepak / 9820723508 /
Deepak Trivedi


Hi, I am owner of flat C-1004 in HDIL Meadows Goregaon West. Please add me in Whatsapp. Regards VS Chadha 9820531147 email- vschadha2@gmail.com
uyt ewr, Apartment Resident 
23rd June 2014


23
dear all, kindly provide your mobile nos and name and email address, we also have whats app group, will add you to whats app, regards deepak / 9820723508 /
Deepak Trivedi


24
Also the rate quoted is Rs 12,500/-. Considering the state of HDIL/Guruashish, it shouldnt happen that the project is in a limbo for years.
Cool Guy


25
Hello Everyone,
Can anyone suggest if this project is worthwhile to buy. They are promising it to be completed by dec 2016.
would appreciate your valuable suggestions. Kindly reply

Ken
Cool Guy


26
Hi Everyone ,
We have also been allotted a flat (D 2502) in June 2010.
I just came across this chat & would like to be included in the group please.
My email id is manasijoshiroy@gmail.com
Any recent updates ?? Please do share .

Thank you so much ,
Manasi
Manasi Joshi Roy


27
I have heard that the work is going on at snails pace. Is it advisable to put further money into the project or get out of it? Has anyone asked for a refund? Ramesh, Mumbai
Ramesh gajria


28
Hi , can you please add me in the google group - eurekaweb@yahoo.com. vinod panjwani - E - 1001.
Vinod panjwani


29
Pl add me mamatasatam@yahoo.com or mamatasatam1979@gmail.com Flat is on A -26 th floor
Mamata Satam


30
Can some one add me to the group -mil_sat@hotmail.com
I have booked a 2 and 1/2 bedroom on the 26th floor...
These guys are asking for heavy amount in cash before the registration.
I believe these guys have CC till the 18th floor ,Is it legal for them to get me registered if I have booked a flat on the 26th floor?
let me know how many of you have got the registration process complete.
Milind


31
i was told that work is in full force
hira


32
Unless I get an invite and accept the same, the mail to the above group doesn't go through. Please do the needful. Thanks.


33
My email ID is kansat83@yahoo.in . Can someone please add me to the Google group? Thanks.


34
Can someone add me to the googlegroup? Have already sent a mail to hdilmeadowsowners@googlegroups.com


35
Hi Can you please add me to the google group. email id - kunjalt@hotmail.com. I have booked flat in D 2104.
Thx
Kunjal Thakkar
Nilesh Thakkar


kindly mail a request to hdilmeadowsowners@googlegroups.com
Deepak Trivedi, Apartment Resident, Mumbai
18th February 2013


Dear Group

I am one of the (unfortunate?) buyers stuck with HDIL.
Please add me to the group and in the mailing list.

I stay out of India but will try best to contribute in our efforts to resolve this
Dear Group

I am one of the (unfortunate?) buyers stuck with HDIL.
Please add me to the group and in the mailing list.

I stay out of India but will try best to contribute in our efforts to resolve this
Dear Group, I have sent request to hdilmeadowsowners@googlegroups.com but have not received any confirmation yet. I have booked C2301 but seems developments are extremely unsure.
3rd March 2013


you are one of lucky person already sitting on almost 50% appreciation of the project value and paid only 20% so far.
hira, Apartment Resident 
12th May 2013


36
tommorow meeting is schedule with hdil management and architect to discuss the floor plans, request to attend if possible
Deepak Trivedi


37
This company needs to learn to respect their customers. We could have easily invested in another project. We should be given a time barred agreement so that we may plan our finances. We all need to band together and take them to court. The last thing they need right now is negative publicity.
Stephen


38
Cost of purchase has gone up due to change in plan. No flower bed. approx. 10 to 12% cost increase in totality.
Rakesh Desai


I have also recieved a letter to visit their office. Are they allowed to change the cost of the apartment at their will? After waiting for so long we should be given a discount not an increase.
Stephen,  Pune
31st January 2013


acc to the new bmc norms ....all other open spaces like flower beds open terraces or balconies will be accounted under carpet area....hence they have increased the carpet area according to the new fsi approvals ....however the same has been passed on to the actual consumer
jay,  Mumbai
4th February 2013


39
Part NOC up to 18th floor is received by HDIL. Understood that construction work is starting now in full swing. i have to still wait for 21st floor.
hira


any updates on the meet with the architect?Did it happen?
31st January 2013


40
Hi, my flat is in F wing. I also got a letter to visit their office to execute agrrement.
Rakesh Desai


41
Please keep me informed as well. I too, have booked a flat in C Wing. On enquiry at the site office yesterday, it appears that part CC has been received. Any update.
vmrathi


Hello Gauri, kindly send me updates on kunjalt@hotmail.com and my mobile is +919008406369. I'm in Bangalore but my brother would surely jioin if there is a meeting.
24th January 2013


hi i have a flat in E wing , i have recieved a letter statuing they are ready with agreements , can anyone throw light on this
jay,  Mumbai
28th January 2013


42
https://groups.google.com/forum/#!forum/hdilmeadowsowners

Dinesh please enroll in the above yahoo group, you will get all updates

We are meeting again on 19th at Bnadra office

Utkaarsh


Hi. please let me and all others members know about any progress from HDIL. Also please confirm me, if there is any meeting on Saturday. 19th. Thanx
16th January 2013


Utkaarsh, just my humble request to you.
16th January 2013


43
Dear All, i see your comments and i also have booked an apartment in HDIL and still no news and no idea what to do with this investment. Can u all include me in the conversation. I newly joined this forum. My email Id: dinesh_sonawane16@rediffmail.com and dineshsonawane16@gmail.com
Dinesh Sonawane


44
Please update me on the next meeting so that I can join you guys... Appreciate the efforts you guys are putting in
Dinesh Sonawane


45
Hi I am Swapnil Modi, I have a flat in E wing on 31st Floor, Please update me on the next meeting so that I can join you guys... Appreciate the efforts you guys are putting in
Swapnil Modi


I guess there are only 28 floors in every wing except D wing
Manthan B, Apartment Resident 
26th December 2012


46
Hi Gauri..please add me to the mailing list as well..I have booked a flat in the B wing and am in the same boat as all of you.

I would like to attend the next meet on 12 Jan . Thanks
O P Jain


sure. thanx.
24th December 2012


Hi Gauri can you please give me your mobile number. Wanted to talk to you. Thanks
lumeena,  Mumbai
26th December 2012


Any news about 12th January meeting??
Dinesh Sonawane, Apartment Resident, Mumbai
16th January 2013


47
Hi Gauri, If you could kindly add me to the mailing list as well my email id is jagdhir@gmail.com. I am currently out of the country hence my mobile will not be functioning.
jagdhir


sure jagdhir. Plz let us know if anyone can attend HDIL meetings on your behalf.
17th December 2012


Hello Gauri, I am Kulbhushan and my cell no. is 9769368158, could you plz add me to the mailing list, so that I can attend the meeting too. Thanks
19th December 2012


thanx kulbhushan. ll let u know the details of next meeting asa we get a call from HDIL
24th December 2012


plz provide your mail id as well for further communication
24th December 2012


Thanx Gauri.. my email is vkt0808@yahoo.com . Let me know if v all can have meeting. Its high time now. Thanks
29th December 2012


HI Gauri. Any news for development? And Mr. Rajesh .. DO u got ne news? Thanx
12th January 2013


48
Hi All,
I was able to speak to Anand and following id the details i received:

HDIL and BMC has worked out the payment terms and now HDIL is supposed to make due payments and receive the CC by 10th January 2012, no other issues are epxected once the CC is received and work is likely to be 24*7 and possessions will be in 2012 towards end of the year

Rajesh Khakhar
9820453488
Rajesh Khakhar


oops....its 10th January 2013 and Possessions in 2015
14th December 2012


Gauri, please add me to the mailing list - rajesh.khakhar@gmail.com and mobile no. 9820453488

thanks
rajesh khakhar
14th December 2012


done. thanx rajesh
15th December 2012


Hi Gauri, If you could kindly add me to the mailing list as well my email id is jagdhir@gmail.com. I am currently out of the country hence my mobile will not be functioning.

Hi Gauri, If you could kindly add me to the mailing list as well my email id is jagdhir@gmail.com. I am currently out of the country hence my mobile will not be functioning.
jagdhir, Apartment Resident 
16th December 2012


Thank-you for your post
sudsak, Apartment Resident, Mumbai
16th December 2012


Any further update. Some sort of CC has been received.
vmrathi,  Mumbai
21st January 2013


49
I think we all need to start considering the actions given in the article below. I beleive "Item# 10. Delay in delivering possession" applies in our case.

http://helplinelaw.com/docs/main.php3?id=RBRE8

10. Delay in delivering possession:

In case of delay in delivery of possession by the builder, the legal options that are available to the allottee are to file a consumer complaint or file a civil suit against the builder for the refund of amount paid to the builder and the interest thereon.
.....
sudsak


Hi are u there in the HDIL contact list? if not plz gv ur no and email id for further communication. next meeting with HDIL is on 12th jan 2013 we are waiting for the confirmation of time and venue from HDIL officials. shall send u details accordingly.
12th December 2012


My wife Tanvi is in touch with you
sudsak, Apartment Resident, Mumbai
16th December 2012


50
Hi I just came across this thread today I have booked a flat in HDIL in the A wing on the very first day of opening and I am also in the same boat as you all. Till date I have been calling up the HDIL fellows and am getting the same above mentioned response. I would also like to join your group. I stay very close to HDIL and have been so far just monitoring the progress of HDIL which has not been showing any signs of progress at all. My Mobile number is 982052544. Pls include me too in the forthcoming meetings & kindlly update me on what happened on the recent 8th Dec meeting .Thanks & Regards. Lumeena Akerkar
lumeena


hi Lumeena pl gv your correct no and also give us your email id for further communication. Next meeting with HDIL is scheduled for Jan 12th 2013. shall let u know the time and venue in due course of time.
12th December 2012


sorry it is 9820525444. My email id lumeena.akerkar@gmail.com thanks
lumeena,  Mumbai
13th December 2012


thanx. shall let u know d details of the next meeting
15th December 2012


51
As already mentioned in the mail sent by Abhinav to the group,
1. we had a discussion between the 10 of us who came for the meeting at Inorbit mall, and later on we went to the site office.
2. We spoke to Kashyap but we got the usual response from him to our queries about the CC and the commencement of work at the site. Later on we requested Kashyap to call Mr.Anand Almedia (AGM) and all the attendees spoke to him on speaker phone.
3. Anand did not give us any firm response but has agreed to meet us in person at the HDIL Meadows site office on 8th Dec at 11:30 AM.
4. Our strength in numbers present at the meeting did impact the attitude of HDIL site office people. They had to sit up and take notice.
5. Hence, please solemnly request all the people who have booked their flats in Meadows to be present for this crucial meeting. Once again the meeting is scheduled on 8th Dec at 11:30 AM at HDIL Meadows Site Office.
Vinay Bhat


52
Gents,

Could you please provide an update of the meeting held today?
Appreciate your response.

Thanks in advance.
Partha De


53
What was the outcome of the meeting at inorbit?
Stephen


54
We are meeting on 18th, Sunday at inorbit malad, time - 3pm to have a discussion and take this matter forward...
Kindly refer all details on the group:

https://groups.google.com/forum/#!forum/hdilmeadowsowners
Abhinav Roy


55
I called Kashyap at the site office this Monday. He was not aware about the status on the CC, and has completely gone back on their earlier update of awaiting for the CC. He mentioned clearly that he has no clear visibility on the date of receiving the CC. On further proding he asked me to get in touch with Mr.Anand Almedia at the HDIL Main Office in Bandra(E). I have tried reaching out to Mr.Anand at 02267888000, but have not been able to till now. Please let me know if anyone has luck in speaking to this person.

PS: Further when I enquired with Kashyap abt the work going on the in the adjacent plot, he mentioned that the work is executed by HDIL and it is for constructing a building meant for rehabilitating the existing tenants of the house which were existing on these plots.
Vinay Bhat


Any Luck on trying to reach Mr. Anand. I tried as well. No one receives the call on this number.
Manthan B, Apartment Resident 
29th November 2012


56
Also, guys, did u notice one thing? Meadows page has been removed from the HDIL website. I really doubt, if they will be able to complete this project at all. Even if they do, it will take 5 years, it seems. And even if they somehow even complete it in 5 years, the construction quality would be very inferior.
Manthan B


57
Seems like I am also in the same boat. Had booked the flat in F Wing back in Nov 2010, but in the past few months there has been no update from the Site Office. Every time I call, I have been told that they have got the verbal commitmment and that they are currently awaiting the formal CC from BMC. Please keep me in the loop regarding any next steps you guys plan to take. Its high time we take an action.

P.S:Incidentally in the plot adjoining this one, the work is in full swing, I recently saw a crane being installed there!
Vinay Bhat


pls join the group...we are in discussion to hold a meeting on the same: https://groups.google.com/forum/#!forum/hdilmeadowsowners
7th November 2012


58
Request ALL to become a member of this group created by Abhinav Roy. Please take this seriously.
Nisha


59
I have also booked a flat there. Please keep me in your loop.
Ajeet Kumar, C903, MEADOWS
AJEET KUMAR


60
hi all, any latest news on this...this thread was started last Nov ie 2011 and now 2012 too is ending. There seems to be no progress from the builder's side. The location is having a haunted look now...think its high time we all take a decision on this SOON.
Nisha


Yes , we should all take a decision.The Senior Managers donot even pick the phone. The site office people say they donot know when the hardcopy CC would come:)
2nd November 2012


61
Hello all..

I have a 3bhk flat as well in D block. As suggested my many people. it is high time we organise ourselves and forma group.

I have formed a group for all to join

Rgds,
Abhinav
Abhinav Roy


https://groups.google.com/forum/#!forum/hdilmeadowsowners

Let us organise a meeting together to chart out further course of action

- Abhinav
28th October 2012


62
Hi All,
I have booked a 2 1/2 BHK at the Meadows more than a couple of years back and the responses I have been getting from Site are similar to ones posted above. I have spoken to both Mr. Dharshak Dalal and Mr. Kashyap, and if I am made to believe, looks like this week and the next are crucial, the builder has got the verbal nod to move ahead (i.e. full CC) only waiting for a formal document from the authorities. If we do not get any clear response thereafter, I am sure it is high time we escalate this issue to higher levels. Needless to mention money does not grow in trees, it is our hard earned money after all. All these info is based on tele-phonic discussions with the two gentlemen I have spoken to over phone during the past few months. kindly keep me in the loop.
Partha De


63
I just came across this thread. Thank u all for all the info. I booked a 3 bedroom apt on the day they opened sales. I met with the manager in July when I was visiting India and was told that due to cc and new BMI rules construction had been stopped. HDIL is being very reluctant in sharing info with the owners. We have a right to know the status of this project that we invested our hard earned money in. If there is any committee being formed I would love to get involved. As previously stated by others on this thread organization is vital. I thank you all for your this wealth of info.
Stephen


64
I visited HDIL site today. Spoke with Mr Dharshak Dalal. He told me that HDIL is meeting with BMC soon to come to a decision on CC. They are hopeful that they will be getting one. He asked me to followup by Oct 15th.

He also said that 3 months back the last sale was made for a base rate of 10750/sq ft.

He said that there is no base for any rumors about HDIL not having any funds. He said that once CC is received there will be progress.

He asked me to provide the PAN numbers for all the people to be on the agreement.
sudsak


thanks for the update since i am not staying in India your piece of info was a relief to us.
Rupesh,  Chandigarh
2nd October 2012


Dear Sudsak , can i have your phone number i will call you . As i want to have a word with you on this. thanks alot
Rupesh,  Chandigarh
2nd October 2012


I'm currently visiting India..u can reach me at 98670 06840 - Sudesh
sudsak, Apartment Resident, Mumbai
3rd October 2012


65
There are lot more questions than answers. Unfortunately I havent got any answers myself but I'm gonna ask more. Does anyone know anyone who pulled out of this project and got their money refunded?
How good are HDIL with refunds? Are they doing it without any fuss and are they paying interest?
J Kewalramani


66
Post your ReplyWhat have you found so far yourself? What do you suggest we all should do at this point??
Bimal Kumar


67
Please let me know about the latest updates.
Ajeet Kumar
AJEET KUMAR


68
Good Day Colleagues,
Any further news on what is HDIL's intention to do with this project, agreements, and any word from their top management??

Bimal Kumar


Hello, I called up the site office two days back and they said that they are expecting CC by this month end. Did anyone else get the same answer?
15th September 2012


YES I TOO CALLED AND THEY SAID THE SAME THING HOPE THEY R RIGHT
16th September 2012


69
i had booked a flat in B wing at meadows.pls keep me in the loop.
thanks
deepak guha
deepak guha


DONT KNOW BUT TOI CAME OUT WITH AN ARTICLE THAT MHADA WAS GOIN TO CANCEL THE REDEVELOPMENT OF MHADA PLOTS OF BUILDERS WHO HAVE NOT COMPLETED THE BUILDINGS AFTER BEING AWARDED THE CONTRACT
10th September 2012


70
Can we add or create a yahoo groups , so we can all be updated and i f needed meet up
Utkaarsh


Does anyone have any further news/updates?
25th August 2012


Please create an yahoo group, as my money is also not refunded by HDIL, i am doing followup with them from last 6 months..
Mufazzal,  Mumbai
5th September 2012


71
Dear All, i see your comments and i also have booked an apartment in HDIL and still no news and no idea what to do with this investment. Can u all include me in the conversation. I am staying out of India
Rupesh


72
can we file a PIL against HDIL.. its been 3 years that i have put in the monies and i am sure we all have. in all the queries addressed by our fellow buyer friends, there is no definate repsonse from any HDIL representative. we should put forward our queries to HDIL directly or have a Buyers meeting with the MD so that we can get clear answers once and for all.. i am sure the HDIL management would not like to have a dent to their equity as a builder by dragging this issue and not answering our queries.. we need an assurance now from HDIL on our investments else we withdraw and invest somewhere else. my email id is rajdip1511@gmail.com
Rajiv


yes we should all get together and talk directly to the builder PINTO
16th August 2012


73
Hi, visited the site in first week of August, the feedback as follows:
- all work has been stopped on the site, including work on the MHADA redevelopment buildings
- their feedback is that with the new BMC regulations, the construction cannot proceed without having complete CC of the project. Earlier they used to obtain CC till say Floor 6, construct & then seek additional floor CC. With new regulations, they need approval for the full project
- Added to the same, the new DCR rules being put in place changes the FSI calculations for the Flower Beds & Dry area.

Accordingly don't see any progress anytime soon... On the issue of HDIL vs. Guruashish, if u see the original receipt it says that money is being collected by HDIL on behalf of GuruAshish. This company is owned 100% by HDIL. Even the MHADA boards there say this is a redevelopment along with GuruAshish Constructions
Vinit


74
guys any idea when hdil is getting CC certificate PINTO


hi guys , i am new to the thread.. even i have booked a 3bhk in hdil.. lot of information from all of ull.. thanks.. plz keep this pg alive so v can discuss..
sahil,  Mumbai
9th August 2012


75
31st July Mumbai Mirror - Poor demand and new building norms have forced developers to freeze construction at upcoming projects

Majority of these projects, around 202, are in the western suburbs, with Goregaon (48), Bandra (36) and Andheri (36) topping the list.

Apparently biggest roadblock for HDIL like others is DCR norms...It looks like the project work may not resume unless this issue is solved
M Maheshwari


Hello Friends, Let me also know what steps you guys are taking. I believe they want us to give back the old HDIL receipts and they would give us a new one on the name of Guruashish. did they convey this to anyone else?
4th August 2012


yes they did ask em the same when i visited in July first week
Utkaarsh,  Mumbai
8th August 2012


they havnt told me anything regarding Pinto
9th August 2012


guys do we have pay the service tax they r asking Pinto
9th August 2012


76
We two friends have also booked flat 2 bhk in the project but no satisfactory reply has been given by HDIL, and now the name of hdil is also vanished and guru ashish constructions
Kamlesh Verma


77
Please someone let me know the outcome of meeting with HDIL dated 29.07.2012.
AJEET KUMAR


78
Hi guys i have also booked in the meadows in the D wing and waiting for best to hear and happen.
joskd


79
Can we go legal against HDIL and ask them to pay us the interest on the amount invested almost 3 years back. i had heard of some Court law which was passed some time back which said that in the event the project gets delayed beyond a stipulated time period, the resident is liable to recieve interest for the amount invested.
do we have a legal guy in our project who can guide us on this
Rajiv


hi rajiv
plz dont b in hurry to back off. There is no point in going legal. at least at this stage. you ll b wasting ur time n money. As we know from the press reports, HDIL is facing financial crunch. I think its lil difficult either to get r money back or interest on the funds v ve invested for three yrs. I suggest u spk to Mr Nikhil Agarwal (c the first post on this page) or plz let us know ur e-mail or contact no aeap
28th July 2012


please add me also in the group i am also facing problems have booed in e wing my email id is kamlesh7771@rediffmail.com
Kamlesh Verma, Apartment Resident 
31st July 2012


80
hi Guys. i spoke to someone at HDIL today and they said they still havent recd the CC to commence work. they are saying they dont know when will they get the cc and have said either to wait or to pull off the monies if one wishes.
Rajiv


the same was the reply given to me over phone yesterday
Kamlesh Verma, Apartment Resident 
31st July 2012


81
This is great news for all new prospective home buyers.
Maharashtra OK's housing regulatory Bill
sudsak


Do we have any further updates on the project? We are nearing July end :)
20th July 2012


82
Hello Nikhil Can you please share a copy of this letter. I sent you my contact details earlier this week. Thanks
8th July 2012
Comment


Hi, Nikhil. kindly share the contents of the letter with me on jmkatti@gmail.com. thanks
Jayant Katti, Apartment Resident, Mumbai
9th July 2012


please forward to me also vermakamlesh@sbi.co.in
Kamlesh Verma, Apartment Resident 
31st July 2012


hi Nikhil can u forward a copy ,my mail id is tiwari.seema30@gmail.com.We have booked a flat in E wing.
seema tiwari,  Mumbai
24th August 2012


83
I also want to participate in process of writing letters for the delay. Please update me frequently.
AJEET KUMAR


Hello Nikhil
Can you please share a copy of this letter. I sent you my contact details earlier this week. Thanks
8th July 2012


84
hello Nikhil

Thanx for your email which gives updates of the latest proceedings. Letter is neatly drafted and covers all our concerns. Thanx for the initiative.
Gauri Pansare


85
We are writing a letter to HDIL. Let me know if any one of you is with me
Nikhil Agrawal


please give me a copy kamlesh7771@rediffmail.com or vermakamlesh@sbi.co.in
Kamlesh Verma, Apartment Resident 
31st July 2012


hello, request you to share the copy of the letter sent to HDIL. my mail id is nishaabin@gmail.com
Nisha,  Mumbai
26th September 2012


86
Permissions required for construction in Mumbau. FYI

http://www.doingbusiness.org/data/exploreeconomies/india/sub/mumbai/topic/dealing-with-construction-permits
Nikhil Agrawal


87
I happen to come across this. "Civic authority BMC approves 78 skyscraper development projects in Mumbai (Jun 19)"

I will followup with the site office and want to know if our site in either included or pending. I will post my findings soon.
I suggest if others on this forum did the same, we can compare the responses.
sudsak


88
I have booked a flat No. C 903 in April, 2011. Until now no further installment has been asked by the builder to pay. Please intimate the next date of installment and progress at site.
AJEET KUMAR


I called them yesterday. AS you are aware, the conswork is on a complete stall. I believe as per the new rule they cannot start construction unless 100% CC is received. They stated that the news is awaited in the 1st week of August.
25th June 2012


Guys..... pls go thru article below to understand how the builder can screw us as the agreement is not yet signed
http://articles.timesofindia.indiatimes.com/2012-06-23/mumbai/32381605_1_builder-maharashtra-ownership-flats-act-complainants
Jayant Katti, Apartment Resident, Mumbai
25th June 2012


89
@ Yes JMK we better organise ourselves.
@ JK the allotment letter has been issused during the initial down payment
@ Uttkarsh they have added an additional podium due to which we go higher one floor for the floor we have booked, I had booked on the 8th floor and now the Intimation letter recd for service tax was for 9th floor.

All they are discussing during my last visit to their office was about the agreement which would happen in July which looks bleak.
Lets all keep updating this thread with our visits or communication with HDIL if anyone of us receive.
Thanks to All to keep this thread alive... my email - jeetur@yahoo.com
Jeetu Rohira


90
My main concern is whether my payment is safe. I have paid large amounts in cash and only have an allotment letter and a non letterhead printout as receipt.(only for the down payment, not for the parking). This would be taken care of if HDIL signs an agreement for the flat but there is no news on the same. It would be very easy for HDIL in the future to cancel the allotment citing various reasons and then delay return of the cash and/or return a reduced amount. I think most of us would be in a similar situation. HDIL can go after us one by one without anyone of us knowing about it. I think we need to better organise ourselves and look at different options to let HDIL jointly know of our concerns and prompt them to act favorably. We are 11 on this forum, we need to get other buyers onto this forum as there is strength in numbers
Jayant Katti


91
Dear friends, I have booked a flate one year ago and i have also paid my service tax . This project will take
at least 4 to 5 years to complete. I have visited my self in feb 2012 and met two guys Mr singh and Mr desai
But these guys have not given any proper answer or reply they just keep saying same bulshit again and again
Hdil does not have all the approval and permission for full construction.Please let me know if you have any
new information about this Hdil Meadows, my Email is aslam2419@gmail.com
mo Aslam


92
I'm not currently in India. But I'm heavily invested in this project as well..
I request all of us to keep this thread alive....

Is anyone aware of any other thread or forums for discussions about this project ?
BTW. I have a flat in C wing.
When I last visited in Dec 2011. I got the same crap of approvals from the site office.
Since then we have paid for the Service Tax.

Hoping that the project starts moving ..
sudsak


93
Dear friends, I have also booked a 2 1/2 room flat with HDIL Medows but each time i go there i hear of a new problem. Since last last two years ther ehas been hardly any progress. I am planning to write a letter to the company so that i can get a written reply. I am hoping to get as much support as possible.

Request u all to email me ur mobile no. & email address to, nikhilagrawal83@aol.com

Regards,
Nikhil Agrawal
mobile: 9920146292
Nikhil Agrawal


I am currently out of India, I have booked 21/2 room flat in E wing. I have paid 25% amount. Have not got allotment letter. My mail Id is mbyadav71@yahoo.com.
manish yadav, Apartment Resident 
23rd June 2012


94
Checking again last week, the agreement is still delayed and expected only around September for now... delays still continue as they haven't got all permissions for the constructions. BTW how is the progress of the premises they are building for MHADA as they can't build this one unless they do good progress for MHADA. The plinth level is about 80% complete though work's at a snail's pace with monsoons on
Vinit


95
@m and the response to @m - I don't know how much credibility I can give to comments without a name !
Have you really booked a flat here or you work for HDIL ?!
I think its important that we have atleast one skeptic / cynic on this discussion...
J Kewalramani


96
Hello friends...I am in the same boat as you all..have been visiting their site office every 6 months and they are very calm and patient to respond to our concerns on delay...nevertheless I agree that there has to be some progress now to maintain that same trust and confidence. During my recent visit in early may I was told that they have stopped new bookings until the constructions resumes...good news is that the last booking rate was 10,750 though I am not sure how it compares with Kalpataru ( little better project) or RNA projects..
m


When I went there, the builder showed me the seven flats booked at this rate (Rs.10750) on his system. Not sure about Kalpataru/RNA- but the rates in Goregaon area is anywhere between 12000 to 14000.
7th June 2012


97
@Uttaraksh How do you mean work will commence because of Mhada land?
Why is the builder not willing to do an agreement? They haven't even given an allotment letter. I was also told that they may change the flat alloted to me.
Guys, what do you make of this youtube video - http://www.youtube.com/watch?v=DtYp7gYSm3U
This presentation shows the siddharth nagar project but its nothing like the brochure shown at the time of the booking
J Kewalramani


JK, relax , thats my opinion as it is goverment approved land, two things on the project, first i have the allotment letter , not sure about others, also the flat numbers are alloted , dont see any chance of change, Second ,for the agreement, 90% of new projects in Mumbai are struck due to the BMC commisioner change after Adarsh scam. Thats my view , if you have a problem please be more respectful in addressing
Lastly on the u tube link , it is froma broker , not HDIl/Guruashish
Utkaarsh,  Mumbai
5th June 2012


Having said so , we still have a problem on our hands, we have to discuss out a solution for this
Utkaarsh,  Mumbai
5th June 2012


I wasn't being disrepectful to anybody.
Its just my frustration with HDIL. The fact is that there are real issues. There are delays, the builder is not willing to do an agreement. The youtube link shows a completely different plan whoever it is from. I haven't received an allotment letter and I was told they may change the flat alloted to me when I visited a couple of months back.
J Kewalramani,  Mumbai
7th June 2012


98
Agree with JMK. We need to organise ourselves because there is complete lack of transparency. Please share info on this thread if you receive any updates. I was in India a couple of months back. I asked to pull out from the project. They said they will deduct 2 lacs and refund the rest. If I wished to sell, they'll take Rs 1000 psf as transfer charges. And that that was today's offer. If I came tomorrow, the figure might be totally different. Its all smoke and mirrors. I spoke to some local agents and they say that HDIL will NOT refund or agree to do a transfer. When it comes to it, he will put another condition that you can't meet.

Please share any information guys. There is something dodgy about this which the builder is not clearly saying. I am sure there will be no agreement in July either
J Kewalramani


About refund, they told me 1% of flat cost is cancellation charges,
overall i think it is not so bad a situation, as this is on Mhada land, so we know work will commence sooner or later, it is about how much time , I know few friends who have invested in other new projects in Mumbai itself, those have been stopped as well due to OCC
Utkaarsh,  Mumbai
4th June 2012


99
Hi Utkkarsh and Jeetu,

I am willing to join too. Please let me know the Date and time. I would prefer the time between 3-4 PM if comfortable. Thanks.


We need mroe people atleast 10 of us , lets try and gather as many as possible
Utkaarsh,  Mumbai
4th June 2012


100
Dear Utkkarsh, please let me know i am ready to join you...any of the Sundays in June / July... Hope this new commissioner gives us some relief..Just hoping the work commences ASAP .. Living on hopes by Investing such large sum past 2 years.
Jeetu Rohira


101
Guys see if we want to visit them at similar time on a sunday in Jue/July , suggestions welcome, more number sof people will help
Utkaarsh


102
work is very very slow I have also paid extra tax about 50,000.00 look like thay dont have all the approval from bmc pls keep in touch. MO
mo Aslam


Yes, I heard the same- they are stating that they would get approvals in 1.5 months or so . The new commissioner has just taken over. They say its the same state of all new projects in goregaon area. They say by JUly agreements will be signed and current rate is 10750.Hoping for the best
14th May 2012


Guys, same here i visited in mid-may , work is stalled xpected approvals by July, hope for the best
Utkaarsh,  Mumbai
30th May 2012


103
pls ask other owners whom you may know to also to join this group. it seems they had sold out most flats within 1st 2 months of opening bookings. with the excessive delay and complete lack of transperency by hdil, we need to better organise ourselves
Jayant Katti


On checking again, it seems they plan to sign the agreements by June 2012 only- anyone has any further updates/progress in construction?
6th March 2012


Can anybody find out whythis project is getting delayed. Builder is telling all the projects for last 2 years are haing same fate.
manish yadav, Apartment Resident 
6th April 2012


104
Yes they have got the CC till 6th floor , the registration is next year (Jan End / Feb) for sure.. Work has commenced from C Wing .. A & B would also commence shortly.. But he assured the work would commence in full swing with added machines and manpower... Well post the agreement the property can be sold .. by giving a transfer cost to the developer....
Jeetu Rohira


Thank you, Any idea about the D wing( 3 bhk)?
19th December 2011


Any further updates on when the agreements would be signed?
30th January 2012


105
Thanks, Did you also check if they have got the commencement certificate? Did they say the registration will happen this financial year? Have all buildings resumed construction or just one? We donot have any option other than wait, do we?


106
Hello everyone.. yes the work has resumed last Sunday. i went there to their Goreagon site office.. rates also increased to Rs 9750/-. Possesion in 2014 - 3rd quarter . share your views is it worth the wait ???
Kalapatru / Ekta / Vijay Buildrs taken 18 lakhs sq ft from Hdil..
Registration is delayed from the talks I got .. maybe Jan'2012..
Jeetu Rohira


107
Hello,
I heard the construction has resumed.Did anyone go and see?


108
Thanks for the reply- I too got the same reply when I enquired. Do they have the same plan approved ( the one they showed us while booking)? Is the construction on all buildings resuming? Mine is the D wing. Any idea on whether the flats are selling ? I heard the current rate is 9250 per sqft.


109
Checked at their office , there was a dispute between contractor and the laborers , they say the work would commence by 25th November and agreements are getting ready with their legal team , registration should commence in December.
Hope so ...
What are your views .. Have you guys inquired on the same at their office ?
Next payment of 10% + Registration charges in December.
Also the Project has been removed from HDIL website due to Mhada restrictions.
Jeetu Rohira


110
I am sailing in the same boat. Any idea if registration is possible during this financial year?


111
I would like to know as well. I've got my money tied up in that for the last year and a half. Any info would be appreciated
12th November 2011
Comment


112