Q: When will Bannerghatta Road is going to be Widened ?? When is the Metro Rail project going to start is Bannerghatta Road. The Proposal has taken place Longtime back but till now nothing has started in Bannerghatta Road. Let me know is there any latest Status update on this. Thanks..Bangalore Citizen...
Funds have been allocated and detailed report is ready. The private properties that would be acquired for road widening work include 272 buildings, 122 vacant sites and 11 temples.
BBMP decided to widen the road by 35 meters and the proposal was rejected by the state government. The state government decided to increase the width to 45 meters. BBMP is planning to acquire the land through Transfer of Development Rights for which the project is getting delayed.
The Bommanahalli zonal office have to acquire properties for the road widening work. Once the acquiring process gets completed. BBMP will start with the road widening work
The widening of the Bannerghatta-NICE Road stretch has been approved by the BBMP recently. The centre of the road, the road will be widened to about 22.5 metres on either side. At present, Bannerghatta Road is just about 20-22 metres along various stretches and impedes traffic flow.