Hi Lekshmi..the accorded roads in this project include TTK Road, Eldams Road, Kalki Krishnamurthy Salai, Dr. Muthulakshmi Salai, New Avadi Road, Cooks Road, MTH Road, Prakasam Salai, Anna Pillai Street and Pulianthope High Road. i don't have any idea about the stretches but yes traffic will be diverted at these stretches very soon.
Hey lekshmi..The initial cost of this project was estimated as Rs 1447.91 crore. Seven stretches have been dropped out but the cost has not reduced. This is because the delay factor balanced it and added more cost to the original cost. Currently, the revised cost of this project is around Rs 1475.43 crore.
Hi all...i heard that Chennai corporation extended its deadline for the completion of project. Can anybody let me know ...the roads and stretches involved in this project. And what is the cost of this project..??
It was a tough time for the civic body...Earlier traffic police use to disturb contractors working on the sites. This led to many struggles between the civic body officials and police at several sites. Police imposed restriction of not working more than four hours at night along many stretches. Contractors stopped working at the sites as they required more time.
Hi..Sundar ..yes the construction work of storm water drains across 20 key stretches hase been resumed few days back. It was delayed for a long time as traffic police had fear of traffic congestion due to digging work at roads.