Completion status of KG signature flats - Maduravail chennai
Q: Hi proved owners of KG sign. I have booked 1107 of C-block. I inquired KG office about handover date. They coolly say that electricity and water connection not obtained. If they dely more they must pay the penalty as per contract..... kalimuthuk63@gmail.com
Hi All, KG signature city is one of the most attractive destination for those who are search properties in chennai. project get location advantages and those who invest in this location get good return from this area. This project is almost completed . project is suffering from certain delay in pass few month but it is resolve and now unit is handed over to the end user.
hello people! i am proud to say that im now a proud owner of a house at signature city. i kept checking this forum for seeing if everyone was getting frustrated waiting for the handing over as i was. finally got a call from kg office saying to me that my flat is ready for handover. so thought i should share this news with you.... we were so happy! this is my first home.. so better late than never... it is releif to move from a rented house to a home of my own!
Can you tell us how many days have you waited for this project ? I am planning to book an apartment for own . Need little bit of your advice. Kindly share some information which will be helpful to those who are searching apartment like me.
Dear forum members. I like to recall the messages and comments posted by me. I am informed that the Kochi project that I mentioned is not belonging to KG builders who are doing Signature City. I had seen all these projects including KG oxford symphony, Kochi under the same website under the Projects web page of KG builders, which was also misleading. The builders has come forward to address the issue of buyers with some relief measures for Kochi project also which is a constructive move from their side. Thanks
I hope the KG builders projects such as Signature city is going well.They explain to me that these are different groups. It is confusing as all these projects are mentioned under the projects page of the same website. This builder has to bring in more clarity to buyers so that facts are known to buyers.
My flat at Oxford Symphony, Kochi is still not handed over even after three years of scheduled completion. I paid all three years rent and still living in rented house. This great builders has not even paid one rupee as compensation or relief to me. As per my experience, don't trust them. I do not know were it will end up in their other projects
KG builders are cheats, Don't expect any good with them. I booked my flat in oxford Symphony, Kochi in 2009 and was supposed to be completed in July 2010. July 2013 , I am not sure about the possession as they violated building rules and they have no completion certificate. They are also facing vigilance enquiry. One week I am trying to contact the builders, they are not even answering calls... They just sent an apology mail. They are cheats....
Thanks Mr. Gurmeet. I too contacted them and their answer was same. We all join together and request for expediting the water and electricity as well as penalty payment. I was told one of my friend that OZONE in anna nagar paid penalty to the flat owner even though flat owners did not ask them.
Hi, i had a word with the brokers too, yes it is true that water and electricity are yet to be connected. They did not mention about the penalty. Although i think you can have a word with the builder reading the penalty due to delay.
They violated building rules in Kochi and the project is in vigilance enquiry. The project was supposed to be completed in July 2010 and till date in July 2013, it is still in litigation due to building violations. After being delayed by three years and not sure about the further delay, this builder has not even paid one rupee compensation.. Don't believe this builder