Q: Hey I heard that there is some work going on for the Mysore-Bangalore rail road like doubling of the tracks and electrical work. Anyone got details on this? And also will the electrification be done in both cities?
Hi. As of now the work near Paschima Vahini has been completed. The track between Byadarahalli and Pandavapura also has been completed. However, the yard work is still under progress. The track between Pandavapura, Srirangapatna and Naganahalli is still getting laid. Should take a few months to complete.