Construction is stalled for the past 4 months! ! And details?
Q: I own an appratment in Vishwakarma In town.Construction hasn' progressed for the pat four months.Does any one have details on what the problem is and when would they start the construction again?
Yes in the link http://www.commonfloor.com/vishwakarma-in-town-chennai/povp-774473 Possession date is shows as Apr 2016. But I think this could be the case for Phase 2 Apartments. The walls are near completion. Part of the construction blocks was done using porotherm bricks and other part is being done with solid blocks / aerocon blocks. Reason cited : Non availability of material. The 4th floor is kept pending because of this shortage. Given this scenario, the handover could be april 2016, which is a cause of disappointment.
The possession date for phase 2 apartment is June 2017(please check the comment below).April 2016 is for phase 1.I think the reason cited is just a "reason of convincement". I still think April 2016 is not the date of possession. It would get extended. Even the brick work hasn't completed yet!! I am thinking of cancelling the apartment.I don't believe that this is really gonna complete .
Now the date of possesion is again revised (4th time) to Apr 2016 for Vishwakarma intown ????I seriously don't know what is happening in this project.Are they planning to complete it or not.
Dont know what is exactly happening ? I was told it will be around Dec 2015 when they hand over. Where did you get the information about the new date Apr 2016
In the above link , Check under facts you would see the possession date.Last week it was Dec 2015 and this week it has been changed to April 2016...Dont know what they are upto.
Javed -Pavan-Priya ..Hello.I have bought an appartment in vishwakarma in town..The initial date of handover they said was Dec 2014 and it got changed to March 2015.But now it says Dec 2015 in some of the websites for vishwakarma intown !!!! Not sure why they extend. With the current status if they give it to us by Dec 2015 it would be good even though it is a delay..Does any one know if the construction is going on??And would they give compensation for the delay??lets have this group active
Did any one make a reply to this query about the stalled progress. I spoke to the the representatives and was told the reason for stopping "Clearance from CMDA / DTCP as a back lash of the mogilivakkam incident " I some how feel this is not right. The authorities can not stop the clearance unless Vishwakarma is not following specified standards. Also, this is not a multi storey apartment beyond 4 floors. So I think we need to cross check again.
Yes Suresh..I too feel the same..In adfition to this the brick work they started (after 12 months stalled progress) has stopped last week again!!.And the reason I got was that the lift to send the bricks up to the top floor was not working!!!!Do you know what is the process to be followed to request for a cancellation of the appartment?
Thanks for providing the details about this appartment.Could some one please let meknow why the construction is stalled with this project.They havent construction for more than 4 months.Does any one know why this is not happening? Is there any one who bought a house there?
Hi Mr Bala, Vishwakarma Intown is one of the popular residential project in Chennai. This project is located in Kelambakkam, which is one of the prime residential location with decent environment. This location has all daily basic amenities nearby. This project offers you 1 BHK, 2 BHK & 3BHK apartment, area ranging from 5710sq-ft to 1243 sq-ft. Builder quoted price is around 3500/sq-ft. Expected possession of this project is around 2015 March.
According to me, this builder has recently launched In town Phase-2 ,adjacent to this project. Having 3500/sq-ft , this phase will have only 2BHK & 3 BHK. This project has CMDA approval. Banks financing this project are State Bank Of India, Canara Bank, LIC HFL, Axis Bank & HDFC Bank. Expected possession of this phase 2 is around 2017 June.