Mr. Bala Arunkumar, I was told it will be around Dec 2015. Where did you get the info saying Apr 2016?
Q: When I was asked to make a stage payment (wall completion), I asked for the schedule. Then I was told around Dec 2015 when I was at the site. Now you mention Apr 2016. What is happening ? I am truly concerned and appreciate Mr. B Arunkumar's efforts.
Earlier they said, the project would be completed at Dec 2014, with grace period till April 2015....But now they are telling completion would be on December 2016 to April 2016.
Hi, Payment plan for this project what builders had shared with me is as follows:
1. Initial Advance 10%
2. On agreement 10%
3. On foundation 20%
4. Ground floor roof 10%
5. !st floor 10%
6. 2nd floor 10%
7.3th floor 10%
8. 4th floor 5%
9. flooring 10%
10.Handover 5%
Thank you very much for your guidance. It's a well thought through response. and I think the Vishwakarma is one of the renowned builders in Chennai and he will keep his deadline for delivery of this project?