Latest Answer: I too have not got any update on handover yet. Do you know any whatsapp group for Akshaya today. I keep calling CRM team but they have been changing the date of handover from last 3 years. Pls let me know if you have any updates.
Latest Answer: I feel the project is good for both end use and investment purpose. The project has received approvals from all the leading banks and CMDA.
Q:Is this project under hold? same like other alliance projects. no progress observed from last six month. Very poor response from their CRM team on project progress. Still no clarity on when it will be started.
Latest Answer: Hey, I read some where that "Humming Garden Project Awarded As The Most Admired Project Of The Years By ACEF" then what can be the reason that the project is yet to start.
Latest Answer: How big is the project and what are the numbers of floors will be there? What will be the price of a 3 bhk unit all inclusive? Who all have approved the project?
Q:Hi,We have booked a flat in padmalaya project. But there is no progress in this project for the past six or seven months. Can anyone please tell us what is really happening.ThanksP Prasanna
Latest Answer: Hi Prasanna,Last month I visited the site and I found that the construction is going on. What I observed while my visit is that till 5th-floor construction are completed. Yes, I think construction is going slow due to climate and flood in the Chennai.
Thanks
Q:PBEL developers launch a new project PBEL city at Kelambakkam, Chennai. This project offers spacious and skillfully designed 2 BHK and 3 BHK apartments which contain all the modern amenities. Location Advantages: Kelambakkam market: 5 minutes ECR and Kovalam beach: 10 minutes Sipcot and TCS: 15 minutes HCL Technology and AGS Cinemas: 20 minutes Pay Pal Accentures: 25 minutes Global hospitals: 30 minutes SSN Engineering College: 10 minutesPBEL City Project has:Type of Apartment: 2 BHK and 3BHK apartments. Sizes: 1003 to 1733 sq. ft.Price: Starts at 33.80 lacs onwardsPossession Date: 31 Dec 2015
Latest Answer: I visited the project few days back, sales guys seem to be professional and construction is in full swing. Model apartment also looks good. Construction quality seems to be very good, expected since the contractor done by Shapoorji Palonji groups.
Q:When I was asked to make a stage payment (wall completion), I asked for the schedule. Then I was told around Dec 2015 when I was at the site. Now you mention Apr 2016. What is happening ?I am truly concerned and appreciate Mr. B Arunkumar's efforts.