Q: Booked a flat in building shiv sahyadri just adjacent to deepmala ,project of the same builder.I booked flat 3.5 years before and yet even the building that is being redeveloped has not been demolished.I am worried whether they will even start the project ,and also about construction quality of the builder.

Reply

Replies (3)
1
The builder just refuses to give me details as to why project is delayed.his only answer for 3.5 years is we will get cc in 2 or 3 months .I did a mistake to book a flat in prelaunch stage.He verbally promise me that he will allot me another flat in his adjacent building deepmala..but when I went to change allotment letter he refused todo so under the pretext that the partners of deepmala project are different than shiv sahyadri.he is now telljng me to buy flat in deepmala at 8000 psf rate whereas I booked my flt t 5500 rte 4 yrs back
rachu


2
As far as developer's track record is concerned, S. D. Bhalerao Constructions Pvt. Ltd., founded in 1991 with a dynamic vision for the future, the company has made a goodwill for itself in the industry. Engaged in property construction and housing development across Mumbai, S. D. Bhalerao Constructions Pvt. Ltd specializes in quality Redevelopment Projects.

Some of their ongoing projects are Deepmala, Bldg No.50,Vartak Nagar, Vijay Lenyadri, Bldg No.63, Kurla, Satyam, Bldg No.34, Nehru Nagar, Shanti Niketan, Andheri, Sai Krupa, Bldg No.58, Kurla, Multan Bhawan, Vile Parle, Hill Kasa, Shahapur and Padmavati Nagari, At Pimpri.

Some of their past projects are Ashish, Chatrapati, Samarth, Saylee, Lahoti House, Prity Park in Thane, Pritiraj, Sai-Sagar, Sai-Srushti in Kharghar, Om Siddheshwar in Kurla, Pragati in Bandra, Sai-Darshan in Chembur, Shivaprasad in Koparkhairane and Shivner-Plaza in Vashi.

Sankalp


3
Hi,
Nobody can say what is going on in developers mind. So, better visit the developers office and find out the reason of delay. As you are saying that you have booked your flat 3.5 years back, even the construction work has not yet started. Ask the builder for the approvals. Is there any issue with the construction?
Check your agreement whether there is any delay of compensation is mention or not. Take the advice of a legal expert.