DLF HUDA expressway project latest report.

Q: Guys, this expressway is again getting delayed because of supreme court ordered to settle the land dispute near Ambience mall. Kindly discuss.
Reply

Replies (3)
1
After the high court discarded Neha Nursery appeal, HUDA authorities had gone to the site for leveling on 10th April and again on 13th April. In spite of the fact that significant structures were leveled, permissions were looked for by authority for cleaning of trees just recently. It was just two weeks prior that they had uprooted around 100 trees from a large 2664 sq-yd land of Neha Nursery.
Santosh TR


Hi Ravindra Singh,
According to news, IL&FS Engineering officials, which is doing the development of expressway on behalf of DLF, said that the 2664sq-yd of land alongside national highway 8 is vital to this expressway project.
The construction work on one of the passage that was situated to get traffic from Golf Course Road, Sikanderpur as well as Cyber City to the highway has now been slowed down.
6th August 2015


Hi Guys,
According to the a senior IL&FS Engineering officials, this slow down has likewise influenced the road broadening work at the traffic crossing point and kept arranging work of the U-turn suggested from the roadway before Ambience Mall on NH8 on hold.
7th August 2015


Hi Ravindra Singh,
As per latest news, HUDA administrator Anita Yadav said, the authority will separate the land where existing conditions is to be kept up and stop development work. Regulations will likewise be issued to accelerate the remaining work of this expressway project.
8th August 2015


2
Hey Guys,
In the mean time the apex court's order came as a result of Neha Nursery petitions, opposing the Punjab and Haryana high court. The high court had discarded the petitions of Mr Raj Pal Yadav and Krishna Devi, on behalf of Neha Nursery on first April which questioned HUDA's acquisition of their land for the development of road widening as a major aspect of the project.
Dhiraj


3
Hi Ravindra,
As per the latest news, presently it appears this project is not going to be finished by the following due date as the supreme court requested recently to authorities to keep up status quo on a land piece that was obtained by HUDA from Neha Nursery, until a case between the nursery and the authorities is at last discarded.
Lekshmi


According to sources, a week prior to the due date for this Rs 600-crore project was to end, reputed real estate developer DLF had looked for an 1yr extension till 2016 March from HUDA and the state government, referring to postpones caused because of encroachments, land litigations & availability.
Arpit,  Delhi-NCR
5th August 2015


The construction work of this expressway project began in year 2012 and should be finished by 2015 March. On July 23, judges of a division seat, Mr Jagdish Singh Khehar and Mr Adarsh Kumar Goel requested Haryana state government and DLF, to file counter statements. Different parties are coordinated to keep up business as usual, as it exists the day, till further orders from court.
Suresh,  
5th August 2015