Hi..anyone who purchased flats in Cosmos jewels. I'm concerned about the delay in getting the possession.

Replies (9)
1
@Soumya Shankar: As per sales team they have received NOC from Fire department and OC Inspection has been done they are expecting OC by this month end , let's wait and see . If anyone have opted for Soft possession are they charging Maintenance for Month of Feb and March'16?
Bin


OC is received for Cosmos Jewels and possession is started ..
Rahul K,  Mumbai
2nd May 2016


Today, dated 8 july 2016, i have enquired on possession for sapphire, site personnel informed me that, soft possession will be alloted by end of aug 2016. Anybody has the same updates?
8th July 2016


I got an update that for Solitaire Fire NOC is received OC is expected in 2-3 months soft possession will start by Aug End..
sagar,  Thane
11th July 2016


I visited today i.e. 6th Aug. Still only soft possession for Solitaire. OC expected in Sept. Hope this time they follow the schedule.
Mukesh, Apartment Resident 
6th August 2016


You people can join FaceBook group by clicking

https://www.facebook.com/groups/726610640775188/
Deepak Agrawal, Apartment Resident 
10th August 2016


2
Just got an update on 28th Feb that Cosmos Jewels has recieved the Fire NOC and they have applied for OC which they will get it by mid of March
San


That's good news let's hope they really get OC by Mid of March.
Bin,  Mumbai
29th February 2016


Which tower of cosmos jewel have received OC? I mean Ruby, Solitaire A Wing or B Wing etc.? Latest I heard they are will get OC for Solitaire in end of July . Earlier it was June 2016. Hope the best
26th June 2016


You people can join FaceBook group by clicking

https://www.facebook.com/groups/726610640775188/
Deepak Agrawal, Apartment Resident 
10th August 2016


3
Anyone took soft possession for RUBY ?
Bin


yes planning to take soft possession on ist march so that can start the furniture work.

They are saying that they would give the hard possession by end of march . any one got confirmation
San, Apartment Resident 
24th February 2016


You people can join FaceBook group by clicking

https://www.facebook.com/groups/726610640775188/
Deepak Agrawal, Apartment Resident 
10th August 2016


4
Had a word with the sales team and it seems they have not got the fire NOC yet. Worry is that we need the possession before the next academic year as else you are stuck.
Riju Nair


I doubt they will able to give possession by March since they haven't applied for OC yet.
Bin,  Mumbai
31st January 2016


5
Any of member got notification for soft possession , seems sales team has stop replying to email and on call they are giving arbitrary dates.
Bin


6
Hi,
I visited the site today and builder said, possession Mar 2016 for Solitaire and Jun 2016 Sapphire.
Bhushan Lalwani


7
Possession has been delayed by 4-5 months for all the buildings in the complex
MAYUR SAWE


Mayur thanks for the Information , do you have any news related to soft possession ?
Bin,  Mumbai
2nd December 2015


HI Bin,
Well March 2016 is also unconfirmed. Different dates are being given to different customer. When i approached to their sales guy they said April 2016.
Abhinandsavalla,  Mumbai
14th December 2015


Hi Bin,

They are saying they will start giving soft possession in Dec for Ruby and Mar-Apr for other buildings. From my point of view soft possession doesn't make any sense as you will have to pay all the money, o your maintenance will start and you have to pay apprx 80k-1lc deposit.
MAYUR SAWE,  Mumbai
22nd December 2015


Hi, Has the OC for Jewels being received? It is already March 2016.
8th March 2016


Hi, OC for 2 Ruby tower is received and builder has already started giving final possession for the same. Sapphire fire NOC expected by May end and final possession by July end.
MAYUR SAWE,  Mumbai
6th May 2016


8
Are you guys sure of getting possession by Dec'2015. I have booked my flat in "Ruby" and they were supposed to give possession in March 2015 which was postponed to Sept 2015 and now in Dec 2015.
Bin


Hi all,
It is really a matter of sad that developer of this project is no more with us. As per my discussion with them, they said they will be giving possession in March 2016 now instead of December mentioned earlier. Hope, we will understand the matter. If we can wait for 2 yrs. why not 2 more months. At least our developer is not fake.
Ashish Sharma,  Mumbai
21st October 2015


yes, it is really very sad matter. We only blame developers for project delays but we forget our poor system. They have to pay lot's of amount to approval department and politician for passing a project as a bribe otherwise, your project will not be passed.
21st October 2015


Right Aneek,
They have mentioned in his last letter before die that as much as Rs. 800/sq-ft paid to the approval dept. and politician as a bribe to get approval.

Three months before builder's death, minister of state for home Ranjit Patil directed TMC Official to clear Parmar's project, but no action was taken by the TMC authority. He begged state minister for help before killing himself. But the TMC authority has evoked the stop worked order imposed on the project Cosmos Jewels, Ghodbunder Road, Thane.
Ashish Sharma,  Mumbai
22nd October 2015


9
Hi Suresh,
The construction work is in progress. They were initially going to give possession of one phase in October, but due to delay in getting NOC from Fire Dept., it will be given in December,2015 alongwith all other buildings now.
Rakshit


I think Rakshit is Right. I have booked my flat in "Solitare''. I had visited the project last month. It was almost completed. Plumbing and electric work were pending, was expecting soft possession by December'2015.
Ashish Sharma,  Mumbai
13th October 2015


10

Ask a Question