any update on LA CASA noida ghaziabad

Q: anybody demanded for refund from the company? they are not replying at all just making fool of us... please reply with contact no.s so that we can reach to them collectively.
Replies (6)
1
Please add me,too I cancelled it due to delayed construction, mentioned the same reason in my letter or application to them.Three is no response so far
K Asif 9868504257
Kunwar Aftab


I am thinking of going to the court, its our hard money, we could have made it double if we could have invested it somewhere else like banks.
22nd March 2018


2
Guys. I am also victim of delayed this project.please add me for the action against builder . My no is 9811093613
Ramiee


3
Guys. I am also victim of delayed this project.please add me for the action against builder . My no is 9811093613
Ramiee


Please correct no to 9811093623
Ramiee,  Noida
2nd November 2017


4
Hello Guys,
The builder has been keeping us in Dark Since last many years. They are not updating anything except fake promises. Has anyone of you sought refund from them.

Regards....Amber
amber prakash


5
Hi,
I also booked my flat there but nothing is going on. I am also interested in getting refund and i think we should all go together and let us do something in group otherwise they will keep on enjoying our interest.
visaltanwar


According to me, you all should jointly or in a group lodge a complain in the consumer forum and ask for the refund along with the interest. You you will lodge a complain in group it will be more effective as court will take the action fast.
Niraj Shukla,  Gurgaon
9th June 2017


6
Hi Rakesh,
Even i am trying to get my money back as i have booked my flat in 2015 on 20th floor and they have only approval from GDA up to 15-16 floors. I got to know when i enquired later. I am just checking if anyone of us has booked their flats on higher floor here. Builder has shown decency in dealing with customer.
Anand Roy


You are right Anand.
Very cunning builder. They had promised to delivered the project within 3 years but it is already 4 years gone and only 50% construction completed. Currently, no work is going on so me too is looking for my refund. I have dropped many mails to the builder but didn't get any reply.
Bhaumik,  Ghaziabad
9th June 2017


7