Which city are you from? Please select city here.

Rs , sq ft

Removed from Shortlist

My Shortlist ()
Keep track of your shortlisted properties here. Shortlist a property to get started.

delay in project

Q: Hiranandani project - upscale is delayed - what is the compensation being sought from builder

Reply

Replies (2)
1


This is the reply I got from the builder. Though they accept there has been a delay, they are refusing to pay any compensation.

Further to your mail, As you are aware, one of the worst recessions in 2008 & 2009 had an impact on the entire financial system, put a strain on some of our activities which otherwise could have lead to an early/timely completion of the project.

Easwari Nellayandar


Continued:
The construction activities are carried out, in coordination with various contractors like the civil, the electrical, the plumbing, lift erection, fire fighting systems, all that are essential for completion and handing over of the buildings. The impact of economic slowdown put a constraint on their fund flow, which affected timely supply of materials and performance of these contractors. Despite the support we were able to provide them with, it proved difficult for the contractors to perform as agreed with us. This cyclic effect has impacted the handing over, as stipulated in our agreements with you. Due to this unavoidable situation, which prevailed across all sectors coupled with unseasonal rains in 2007 & 2008, and paucity of construction materials like sand due to restriction on mining prevented us from handing over possession as stipulated.
3rd August 2012


Contd;.
In effect this increased the cost of building materials, the increase in USD the cost of imports of finishing materials also went up due to this. As the contract signed with you was firm, we had to absorb the additional costs. Therefore, paying compensation is not possible as the situation was beyond the control of the company.
3rd August 2012


2
Did you get any response from Hiranandani for compensation. I too think we should get compensation for the project
Ravi


3

Ask a Question
120 Characters Left











    CommonFloor Property Search Mobile App now available on Android, iOS and Windows!