Q: No progress/Slow progress of construction at Turquoise Project
I had booked a flat at Nirmal Lifestyle-Turquoise which was promised for delivery in 2013 but till date the construction has been stopped because of some pending approvals. The approvals were supposed to come by June'2012 but they are still pending in August 2012. Construction has not progressed till date beyond the 2nd Slab for which we have already made 55% of the payment to the builder. Projects by other builders which started at the same time are nearly complete. Pls advise when would the construction start again or if it has started then pls upload latest photographs of the site.. thanx
Hi Sandeep, this has become a common problem with all projects.. Before getting approvals only, the builders sell flats and announce completion date. But once the approvals are delayed buyers have to face loss..