Info about Mysore road flyover

Q: Till when Mysore road flyover will be closed. Please update

Reply

Replies (5)
1
All the 14 joints will be replaced at a cost of Rs. 2.65 crore. Replacement of each joint will require at least five days. The work of replacement is being taken up in phases to ensure that commuters are not inconvenienced
anusha


2
The renovation work was taken up in March 2012 and the work about to get over by January 14. But still now the renovation work is still on.
Ramesh Reddy


3
When is the construction work suppose to get completed as it is creating problem for commuters?
Monika


4
Hello Everyone, the same stretch was closed on January 8 as Bruhat Bangalore Mahanagara Palike (BBMP) was planning to replace the expansion joints. For one week, commuters will have to find alternative routes as BBMP has temporarily closed a 2-km stretch for maintenance work. There was a huge traffic pile up in City Market, Chamarjpet and commuters were confused as they were not updated about the traffic diversion. There was no traffic diversion signboards or announcements.
Ravi


5
The Mysore Road flyover, built in the 1990′s, will be closed till February 1 for the renovation work between Royan Circle and Sirsi Circle
poornima


6