Rs , sq ft

Removed from Shortlist

My Shortlist ()
Keep track of your shortlisted properties here. Shortlist a property to get started.

Antriksh Golf View-2 Review

Replies (5)
1
The builder offered possession in 2017. The builder has used sub standard material. Our curtain rods has fallen thrice. We had to re plaster the kitchen twice to install the chimney. There is shortage of parking space and the builder is pushing the residents to share mechanical parking. So 2 flat owners will have to share a single parking. The flat design is very bad alot of area has been wasted in the balconies. No sufficient space in the wardrobes. The builder has constructed additional floors without the knowledge of residents now forcing the residents to sign NOCs on the behest of getting registrations done. Do not buy!
Nikhil


2
Hi everybody, please upload the pics of project site of AGV-II, sector-78, Noida.
DEVENDRA KUMAR


3
Hi everybody,
The current property rate in the locality is between Rs. 5150-5500 sq-ft. And 95% of the units have been sold out.
Wahi


4
Hi,
Can anybody give me the construction updates of the project? I have a unit in AGV1 hence I am really concerned. Not sure AGV1 and AGV2 are going to be hampered by this latest order published in Times Of India.

It was mentioned in the news that almost 20,000 homebuyers in Noida face a delay in receiving possession of their completed apartments. This is due to a recent judgment by National Green Tribunal, which prohibits Noida Authority from giving any completion certificate for projects within a 10km radius of Okhla Bird Sanctuary.
Geeta


Hello Geeta,
I did visit the site , recently and found the progress to be good. The Tower basement concealment and ground level elevation work was in progress. The No. of workers at the site were noticeable.
Mukhesh,  Noida
1st August 2014


@Geeta,
But i dont think it will have any impact on sector 78....only the projects around 2kms of okhla bird sanctuary will be affected by this...
Kasturi,  Noida
1st August 2014


5
Hello Saran,
It is right that they are delivering this project by March'2015. I have booked a flat in L tower. As per construction manager at site they will start giving possession by Diwali 2014 for few towers. He was very confident.
Mukhesh


6

Ask a Question
120 Characters Left











    CommonFloor Property Search Mobile App now available on Android, iOS and Windows!