Hi all , I just want to highlight the calculation of EDC and IDC in ground level . 1. calculation of edc is depend upon FAR(Floor area rate) value. ex. FAR value of Haryana is 1.75. FAR = 1.75 1 acre = 43560 sq feet Total permissible area= 1.75 * 43560 = 76230 sq feet
Hi Saurabh, EDC and IDC is the fixed charge taken by state Govt. In alwar the EDC charge is 7.70% which is fixed for all kind of land but IDC is varying from 9.90 % to 13.30% depending upon the size of the land.
Hi Aveek, You are absolutely right and further these charges are paid direct to state government by the developer for developing the infrastructure and external areas for the project. The charges vary from state to state.