Sobha City increase in Electricity charges

Q: I have a 2BHK in Mykonos, I received an email from Sobha that the electricity connection is getting delayed and they expect that the KPTCL charges are going to be increased. Did any other Sobha City owners get this intimation and are we expected to pay beyond the agreement rates?
Replies (5)
1
From: Kakumani,Bala
Sent: Monday, June 22, 2015 6:02 PM
To: Mykonos3
Subject: RE: Sobha City Mykonos 7051-Sub Station

Hi Tapan,

Sobha has agreed to provide power supply which includes laying the cable from location ‘X’ to location ‘Y’ through BESCOM and now if the location is changed for any reason that’s not appropriate to charge it on the customers. If laying the connection from Manyatha is having issues then Sobha should have approached more aggressively with BESCOM in the meetings and made the decision to tap the connection from Yelahanka much before itself so that all below work would have completed before the project completion timeline rather waiting for 2.5 years initially from Dec’2012 to till date.

Also, DGs are meant to be used occasionally when no power from BESCOM, but not to be used round the clock 24x7x365 days, this will deteriorate the DG life as well along with increasing the maintenance cost.

Thanks,
Bala.
Bala


2
Here is the concern that I have put across to Sobha for additional sub-station charges and the response that I received from them. It would be great if all customers raise the concern so that they will revise / reduce the charges:

From: Mykonos3 [mailto:crm.mykonos@sobha.com]
Sent: Tuesday, July 07, 2015 5:14 PM
To: Kakumani,Bala
Subject: RE: Sobha City Mykonos 7051 & 3094 : Sub Station

Dear Sir,

Further to your mail below;

With regard to the BESCOM supply, it has been adequately covered in our initial note forwarded on 18 Jun 2015. We have no further comments at this point of time. It is only due to our constant and aggressive follow up that we have managed to finalise the connection ex Yelahanka Substation.

The utilization of DG and payment towards the same will be discussed with the Adhoc Association as and when formed.

Assuring of our best service at all times.

With warm regards,
CRM Team
Bala


3
I have also received the letter and final demand letter. Are we going to pay for this?
Ramzan


4
Hi , I also received same email. Looks like handover date will also be delayed due to this. Any idea?
Asma BCube


Hi Asma, Any idea when is the builder planning to handover the apartments?
Manjunath,  Bangalore
12th August 2015


Hi Manjunath, The project will get completed phase wise. Which phase are you looking for?
Sachin bhatt,  Bangalore
27th August 2015


Oh Okay!! Can you help me out with the construction work of Mykonos?
Manjunath,  Bangalore
28th August 2015


Construction work is completed and electrical work is under progress. the whole project is expected to get completed by 2016.
Sachin bhatt,  Bangalore
28th August 2015


5
Hi Rao, You can join the Commonfloor Group, of Sobha City Mykonos, Thanisandra Main Road by clicking on this link http://www.commonfloor.com/sobha-city-mykonos-bangalore/covp-91xbr1 and http://groups.commonfloor.com/ and get in touch with other owners who have already booked a flat in this project and discuss about the same.

Commonfloor.com's apartment management software is absolutely free of cost, Anti spam and provides complete data security and privacy(http://www.commonfloor.com/apartment-communities/pricing).
To find the benefits of joining the software please find this link ( http://www.commonfloor.com/apartment-communities/benefits-owners)
Already 1 lakh apartment society are using Commonfloor Groups to bridge the gap of communication among the owners and MC ( Management Committee)
CommonfloorAdmin


6

Ask a Question
120 Characters Left











    CommonFloor Property Search Mobile App now available on Android, iOS and Windows!