hi I have booked Adarsh Awas Yojna, Phase 5, tower 2. The construction has not started but the loan has been sanctioned by Bank of Maharashtra. Is it an approved project?
If there is any whatsapp group for this project, I would like to to be added . Please add: Deb 9310338939
Hi Roma, +919289080002 Mr sumit grill, you can contact him, he is a admin on whatsapp gp,in that gp we have 256 members and 2nd we hv one more gp. Note:- you need to show screenshot of ur flat numb with name becaz we dknt want to add any builder or agent. Thanks Mohit Gupta 9911716706
1. I had applied for a Dwelling Unit under Amrapali Adarsh Awas Yojna at Amrapali leisure valley pvt Ltd through Investors Clinic in Dec 2015. Two units were allotted to me by them in Techzone IV in Phase 4 and 5. 2. No work has commenced since then till date. There is no response by the builder or Investors clinic on the present status of the project. 3. 20 percent of the amount has already been taken by them amounting to about 16 lakhs for both the flats through investors clinic.The entire amount is through bank transfer and i am holding proper documents and receipts for the same. 4. On contacting it has come to light that these phases of the project have still not received appropriate sanction from competent authority to start the construction. Legally no company can float a project till proper approval is obtained from the Govt. Pl add me in the whatsapp and other forums group Anurag Sharma 08872077170
Hello, I am Dheeraj. On 20th Feb, 2016, I have also booked a Flat No. U2-0604 in AAAY, GH-02, Tech Zone-IV. Since then I have no information about loan, construction status etc. Please add me as well in the whatsapp group. My number is 9891315154.
Hi All, I have also booked 2BHK in the month of Feb 2016. I do not have any information on the load sectioned or not. Please add me as well in the whatsapp group.
HI, I have booked the flat in AAAY in dec 2015,but I want to withdraw my booking,seeing the position of amrapali,as it is not giving possession...I got the information from customer care that booking amount cnt be refunded..i have paid only booking amount. Any one can help in that...IS any one there who is also cancelling the booking.
hello every one ...is there any buyer of AMRAPALI ADARSH AWAS YOJNA ....If any then we have to make a group and requested to all please join my self sumit gil 9289080002.
Hi Mohit, I think you should visit the project site and then take your buying decision. Once, you satisfied with their other phase's construction quality, connectivity, locality and location advantages then you should proceed. Thanks.
Hi Prreti, You are right. I checked. Mine is in R block. Corner tower. 30th floor. work on phase 2 has started. Went there last week. I think Podium or basement is constructed. For phase-3 there was just the same excavation going on. And now Amrapali has started booking Phase-V.
I think every buyers should visit the project site once before booking their unit. Money once goes will never come back.
Actually my concern is Loan funding. i have applied for loan in Bank of Maharashtra. but According to Bank manager he told me Amrapali not Proving some approval paper for Phase -5, R2 Tower. So he can't be proceed further. I want to know that why Amrapali is not Providing all approvals to Bank.
And one more thing is there any Forum or WhatApp group/FaceBook? so we can discuss our query.
Hi Mohit, 3 years have gone by and even phase-1 has reached maximum of 6th floor. It seems to me that they are only launching phase to arrange for some money. I don't see any serious intention on their part to deliver as of now.