Arihant Superstructures Ltd CHEATS home / flat buyers in BIG way. why?

Q: Arihant Superstructures Ltd CHEATS home / flat buyers in BIG way. Government is just silent too.
-See they take advance from buyer showing all good things.
-They take 20% cost of the flat before '' Agreement for Sale'' Registration.
- Now buyer will object to the draft of '' Agreement for Sale'' as it is ALL IN FAVOUR of builder. violating Government approved modael '' Agreement for Sale''
-Buyer will go to court, Builder with his panel of advocates / paying up where needed, oppose it & after 20- 25 years, judgement comes to refund money. This money is worth 5-10% of actual value as flat cost has jumped to 2000 %, original buyer is Dead too.
- MH Gov officers / are on the side of builder - you know why...
How will poor buyer get justice.. Write to PMO portal.. see results too..
Replies (2)
1
Hi Anushkha,
I think possession date is not over. A buyer can file a case only when the project is delayed by more than 6 months. So, better buyer should put pressure on builder for timely possession in stead of filing case. Arihant Amisha is under construction project and date of delivery will be December'2016.
Devika


2
Better, you form a what's up group and gather all the flat buyers. Visit the developers office and ask for the possession. If you are not getting any positive response from builder's side then write a mail asking for possession with delay interest. And file a case against the builder of in-deficiency of service and delay possession.
Anuskha Chandan


3