HDIL will delay the project, they claim that the 42 storey tower will come, but the rusted rebars used for the columns without any anti rust coating. they delay the project ,earlier to some they said possession in 2012 and some others it was 2015!! they demand back 20% with some and 40% with some also nil to someone. Their first project BHANDUP DREAMS IS THE GOOD EXAMPLE TO THEIR POOR QUALITY WORK.Let us join the fight for the poor flat buyers common cause. Dear valued flat buyers in WHISPERING TOWER,
Let us open the eye and unite together to fight the right.
they may delay the project beyond 2015. As per last survey in NOV 2011, they have not sold even 15% of flats. They confirmed to me personally that they do not encourage brokers, but i surprised to lot of brokers are working for them. regards.
Hi I have also booked a 2BHK flat in Whispering towers,we just visited the site yesterday to check the status of the work... But nothing has been started.... And the sales person is telling us that you will get the possession by 2019... Can you please add me in the Group.... My email id is preeti.nirgude05@gmail.com and contact no is 9819096469
Hi, I have booked the Flat in HDIL Majestic Tower on 20th Floor. Please form a group, we should get together and raise our voices about the delay if this project.... prajesh.kadam@gmail.com - 09967788100 We also form group on Whatsapp
Hi ! Please add me to the group.my mail I'd is suhasjoshiin@yahoo.com and phone number is 8860082100 You have taken good step to form the group.regards Suhas Joshi
Hi Amol, I have also booked flat in majestic tower. Kindly add me in group. My mail ID is vinod.dwiveedi@gmail.com
10th November 2016
Dear Amol, I have booked a Flat in A-Wing in October 2015. Pl. add me to your group of Majestic Towers, Nahur. My Email ID: amullya29@rediffmail.com My phones: 9869433294
Hi All,,I am planning to book in Majestic towers. They tell me it will be by june 2017. Do you think possession will happen by then? No one says the exact reason of delay. Hope the construction quality is of good material.
Hi Kiran, BUt most of the property portal have mentioned that possession date will be in mid 2017 but how can they handover on the specified period as lot's of work is still pending.
Hi All, I booked a 2 BHK flat in Whispering Towers in 2012. After long waiting finally they started the registration process. I did my registration and after registration i looked at the documents and found that the Loading for the flat is 40% but i remember when i booked the flat in 2012 they said 30%. Can anyone confirm what was said to you during booking flat in 2012. Thanks. Prabhakaran
Hello Sir, Before registration why didn't you check the required document. Now, the builder is safe as you have sign the agreement. It is always advisable to check all the required documents carefully and read all the clause.
To avail best dealm on it list your requirement here or you can call on this toll free number (1800) (180) (180) (180) Or You Post your Requirements to get matching properties details on your Email and Mobile.
recently I got a letter from them stating that podium level 2 is also completed and we are asked to pay our next instalment accordingly. Looks like they have increased the speed of the work. Hey guys.. any news on when will they sign the agreement.
They have suddenly increased the size of the Flat in Phase I and the cost has been escalated so much...I received a letter in May that according to new DCR rules flat area has been increased...There is no update on Construction..And I dont think possession will be given even by 2020...
Hi. Is there any update on the project? I am lookIng to invest in this project. Please advice. I am a recent graduate and I want to buy a flat that could be complete around 2015.
NO PROGRESS, 42 STOREY . MINIMUM 1 MONTH PER FLOOOR=42 MONTH++ 10-18 MONTHS FINISHING SUCH A MEGA TOWER++ 6-12 MONTHS OC, WATER ELECTRICITY ETC ETC????
PLS COMMUNICATE , ALL DOOMED TO LOSE 19-20 LAKH OR PROJECT MAY GO TILL 2020.
Hello Mr.Shetty, is there an update on the project? I liked this project after looking at it. But reading the comments here and on other forums, I am hesitant. HDIL is a reputed builder after we see that they have completed many projects in Mumbai. Also, the one in Nahur - Majestic Tower is getting build at a quick pace. Do you know what's the problem with the Whispering towers?
Also, my parents visited the site couple of weeks back. They said they do not take anything in black. They will 10 lakhs during the registration and another 10 lakhs after a month. And that's when we'll sign an agreement. They assured that they will continue with the construction somewhere around 5th Feb and then it won't stop. Estimated complete date around DEC 2015.
definitely it will go beyond 2016... infact plint is not complete... already 2yrs gone by from initial launch.... project will not even be ready by 2016... 4 yrs very short time looking at current state of affairs on the site
No, I am not an owner in this project. But you can join the owners group and meet the other owners and discuss these matters. To join the group click Join Owners group of HDIL Whispering Tower.
even i have booked a flat. Can i get further details my email address is geeta.venkatesh16@yahoo.co.in
,
Apartment Resident
18th August 2012
hi, i have bought a flat in Whipering towers. but afraid it is not going to be ready even by 2015... it is going at snails speed... can we owners in HDIL whispering towers meet and organise a meeting with the builders to know the status or proceed with RTI for this
hi i also bought a flat in Whispering towers, and am afraid that it is going too slow and not sure what is the actual reason. Think all owners should go to RTI