Why I am not getting project progress report for Mantri Royale

Q: I bought flat on Block A with a commitment from GM,sunil mantri group for getting it ready for delivery by 2013 end. During Agreement time there was no clarity on possession and dates given were really weird.on my visit in the month of MAY 2013, getting a shoking news : the complete sales and project team is been sacked by new GM ???? i had a sitting with Mr. MIR, New GM and instead of giving a word of assurance he made it clear he cant deliver my flat not even 2015.
I have already paid them 36L and now i am so much confussed to pay then any addition penny without they send me project progress report. My wife and me try to reach top officials but no reach. SUCH A WORST CUSTOMER CARE WE NEVER EXPERIENCED IN ENTIRE LIFE.
Yesterday, I got a demand letter from them for another 13L where there is no progress happened since last 5 months. dont know how to respond this issue.

please help any one address this issue !

Warm regards,
Sunil Nair
sunilnair0505@gmail.com
Replies (4)
1
Dear Sir,
Have you visited recently and is there any progress on this project?
Ramakrishna


if I am not wrong then the project was suppose to get completed by this December. Any idea? Is there a delay in possession?
Mithilesh Roy,  Bangalore
1st December 2014


2
As per your statment that you have personally met Mr. Mir and he did not give you any assurance regarding the possession and mentioned about 2015. i have met him regarding the same where Mr. Mir clearly denied meeting any Sunil Nair and making any such statements.Then i personally went to see the project progress where Mr. Mir also accompanied me and i find that all the infra work is complete and they are starting with the painting and flooring work and we can expect the possession by latest by March-14.
Sakshi Banerjee


I hope you have occupied your apartment by now
Ramakrishna, Apartment Resident 
12th November 2014


3
yes you are right the project was supposed to get completed by mid of this year but I think there is a delay in possession. Now it has been shifted to 2014. I do not know how much the news is confirm and the builder is also not picking the call
Varun


4
Hi Suni, I think all the buyers who have booked a flat in this project should form a group and talk with the builder if all the buyers are facing same problem. Even you can take legal help from for your legal expert.
Dhiraj


The project was suppose to get ready by this year. Did the builder gave any update as and when the project is getting completed.
Saran,  
27th June 2013


5