Rs , sq ft

Removed from Shortlist

My Shortlist ()
Keep track of your shortlisted properties here. Shortlist a property to get started.

When will this project started in 2007 complete??

Q: I have an apartment in this project . its 7 years and still not completed

Replies (2)
1
Dear Legal in SI Westfort Garden.
You stated that both blocks will be completed by December 2015. We the prospective owners are still waiting for delivery in July 2017. Are you aware most of other SI Projects are long long delayed. But promoters continue to lead comfortable lives.
Mathew Chandy


2
Hi,
Yes, the project was delay due to some legal issues but now the construction work is going on. This project has two blocks and both the blocks will be delivered till December'2015.
Komathi


Thanks for the Update, I have emails in which i have been assured of completion dates on a yearly basis from 2010. I have lost faith now on SI . Now i am being asked to take over the apartment eventhou the work on amenities are not complete and no Possession certificate and other clearance from Muncipalities. BEWARE ............................ I have paid in full even the maintenance charges for 1 year. I have been FOOLED inside out.
Thomas, Apartment Resident 
11th July 2014


Hi all,
Here are few projects of the Southern Investments Pvt. Ltd in and around Kochi:- in Tripunitura 2/3 BHK, cost around 80-85 lacs, Kakannad-3BHK , cost around 55 lacs all inclusive, Edapally-3BHK, cost around 75 lacs, Kalamassery-Villas, cost around 1 crore.
Sreekutty Nair,  Kochi
11th July 2014


3

Ask a Question
120 Characters Left











    CommonFloor Property Search Mobile App now available on Android, iOS and Windows!