for KM 15 as per contractor work will be finished by July 2017 and as as per CRM by Sep 2017. lift is working now. Stairs work finished only internal work is remaining.
Hi Anil, There is no update on towers 54 plus...i do go to Kosmos once a month. The only towers which show any progress in this block are KM-53 and KM-54. I have a unit in tower 46. No work is going on in this tower.
Hell Khushbu, I met with FMG Gopal Verma on last Saturday. He informed that material and resource will be available from last week of April. What they are saying to you? Did you get registry date from Jaypee?
Well Gagan, I was told the same thing. My registry date is on next week, 24 April. After the latest round of funding, I hope they would start working on our units. In case you get any further update, please share.
Hi Anil, No construction work is going in Jaypee Wish Town as all the contractor stop working as they did not receive their payment. As long as money infusion does not happen, there will be delay. There is a chance to make fresh money infusion during 3rd week of April.