Wrong information provided on your web site.

Q: In the web site http://www.greenfieldcity.com (Frequesntly asked questions by the buyer) segment completion time is given as follows:
Phase III, Block Name: Elite, Block Type:B, Block No:22. Possession time(plus six months grace period:June-2014)
But as per letter of offer it is clearly mentioned that " the building shall be completed by the builder within day of 31st January 2014, pulse a grace period of 6 months subject however to force majeure". Since 08 months no progress had been made which is indeed very slow. Is there any detail time schedule to complete the phases? Otherwise how we will follow up?
Replies (6)
1
What kind off wrong information is provided in the website ?
prithiraj Chakraborty


2
Uptil now greenfield is just giving reciepts and allotment papers on his letterpad. Is that OK or one should get written on the stamp paper. Or the correct procedure is at the time of possesion. What else (legal papers) need to get from the builder during possesion.
Parvinder Singh


3
On wht value will stamp duty of MIG Classic flats be determined in Greenfield. Will it be on Market Value or on allotment amount.
Piyush Gupta


I too want to know as i have booked a flat in classic Block 63. when this stamp duty money has to be paid and i will recieve after the last payment of during possesion.
24th April 2013


4
Hey, dibyajyoti, can I have your Cell No. I am also allottee in B-22 of Green field. My contact no. is 09560050270.
avgrao1


Hi, Dibyajyoti and avg rao I am also the allottee in B-22. When the builder will give the possession of 22 block. Can be create a group of Greenfield Block 22 to discuss any problem faced by allottee. ajay kr shaw My contact no is 9830059724
AJAY KUMAR SHAW,  Kolkata
28th March 2015


5
hi, mr. bhanuprasad, overall response to this project is very good, provided by a very reputed builder. But, after posting this question, I have received a email from the greenfield management that the hand over date were postponed by six months. This rescheduling is being done in the span of one year. There are more than 2 yrs left, how many rescheduling is going to be done I don't know. The pace of the demand is also very slow which is based on the progress, since 8 months I have not received demand for completion of ground floor casting. I fail to understand the reason from such a high class and one of the best builder operating in this metro. You should definitely consider this project but with a clarification in this issues with the builder.
Dibyajyoti Saha


6
Hey Dibyajyoti, I am planning to shift in Kolkata so was looking for some ongoing projects. I liked the project Greenfield City how they have displayed it in the website. What do you think will there be delay in the possession? Need some reviews regarding the project. Thanks.
bhanuprasad.bharadwaj