Q: Status of Sunteck Orion in Airoli- Delay in commencement of work for lack of approvals? When will this project start. Its been a year since its prelaunch and i hear that it does'nt have required appropriation about your Question.

Reply

Replies (52)
1
Hi everybody,
Can anybody tell me about this project? Have they started the construction work or still waiting for legal approvals?
Miraniyatin


Hi Miran,
This project is on hold and still waiting for Intimation of Disapproval and Commencement Certificate.
Kishore Pathak,  Mumbai
15th July 2015


2
Hi everybody,
How is the locality of Airoli? Will it be a safe deal to invest in Airoli? How is the infrastructural development of the locality?
Ketalpujara


Hi Ketal,
Airoli is a developed residential and commercial suburb in Navi Mumbai. This locality has witnessed remarkable developments in the residential and commercial sector. Airoli was developed and maintained by CIDCO but now it comes under the jurisdiction of Navi Mumbai Municipal Corporation. The rise of commercial activities in this suburb has triggered the demand of properties here.
Rajatrawal,  Mumbai
25th May 2015


@Ketal,
This suburb is well-connected to all major hubs in Navi Mumbai including Vashi and Nerul. BEST and NMMT buses provides excellent services to areas like Chembur, Mulund, Bhandup, Borivali, Vashi, Sion, Thane, Panvel, Bhayandar and Powai. The Eastern Express Highway located on the South provides seamless connectivity to Mulund and other areas in Mumbai.
Rajatrawal,  Mumbai
25th May 2015


3
Hi all,
Can anyone help me with info of new residential projects in Airoli? Also what is current rate of residential property is going on in Airoli?
Chintakpujara


4
Hi,
Approved by major banks like HDFC, ICICI, Standard Charter etc. for home loan.
The other related projects with 2BHK in this viscinity are Green World, Signia Oceans with sizes ranging from 940 sq/ft to 2843 sq/ft.
Bikram


I recently picked up a flat in Bhoomi Colossa in sector 19 , it is fully constructed and has full OC ..1.24 for a 2 BHK ..1230 sq feet
Girish ,  Mumbai
10th September 2014


Hi Grish,
Is the project ready to move and all the legal approvals in place? How far is it from Mumbai Railway Station and the nearby facilities?
10th September 2014


Hey Girish,
Bhoomi Colossa by Gajra Developers Ltd strategically located at Sector 19, Airoli, Navi Mumbai offers 2BHK residential apartment from 1050-1250 sq-ft. Current price is Rs. 5500/sq-ft. Approximate
Sale price will be Rs. 57.75L - Rs. 68.75L.

Project got all the necessary approvals from NMMC and all the leading banks are funding this project.
Bikram,  Mumbai
10th September 2014


5
Hi,
The development of Airoli is happening in a manner faster than any other Navi Mumbai suburb. “The proximity of Airoli to and its access from eastern express highway and Palm Beach road being its main pillars of development. The travel time from Airoli to South Mumbai and western suburbs is shorter with connectivity through JVLR.
Padma G


Yeh,
That is why the rate of property is quite higher here. The current price trend of multi-storey apartment is between Rs. 7650-15200/sq-ft. Rates differ from one developer to another and locality as well.

Similar properties in the nearby localities are Green World, Yash Paradise, Newa Garden, Bhumiraj Meadows, Millennium Avanish Ph-1 etc. in Airoli Navi Mumbai.
Shantanu Kumar,  Mumbai
27th August 2014


6
Hi Friends, I have also booked flat in Signia Orion in Aug 13....Please add me up on Whatsapp Group 9819235720.....What a pitty OR should we called well thought strategy of Sunteck group ?

Ashwin Kharat
Ashwin Kharat


I have already taken my refund. I am not sure when this project will complete...if at all they start.
Ashokchauhan, Apartment Resident, Mumbai
3rd August 2014


Keep away from this builder and even the sales team that each one of us interacted during the booking..they kept on bluffing...even today you visit them...they will sell you a flat.
Ashokchauhan, Apartment Resident, Mumbai
3rd August 2014


7
How can I join the WhatsApp group for owners since I am in the same dilemma as some of you are. My number is 1-602-316-1504
Shikhar Hassani


8
Yes, I received .

Ajit Manke
Ajit Manke


Is anyone taking money back? I wouldn't
Shikhar Hassani, Apartment Resident 
19th June 2014


9
Developer has sent letter for taking money back with 9%interest.
Anybody got letter.

ravindra
ravindra


10
Hi! I have booked the flat in Year 2011...Last when we called they told that everybody is taking their money back with Interest.... My no. is 7718877530..
Anil Gharat


11
Hi Anish / Saurabh I can't add you on whats app group as i cant see you avlb on wats app... Can you txt me on +971526991323 thru whats app
gahlot_vikram


As discussed with you the best option is to send a letter signed by all the residents who have booked in the project..I have also booked the flat in 2011 and has been recieving evasive replies.
VKKUmar
00971504889756
11th March 2014


12
my number is 9833006123
Saurabh Joshi


13
Dear Saurabh - can please share you number please
Pramod


14
is everyone getting there money back from the devloper ? Has anyone got there money back ? Is there any possibility of joint negotiation with the devloper to pay up the lost value.
Saurabh Joshi


15
I have booked a flat in June 2013...My number is +919820521586 add me also in to the whatsup group....
I understand from the office bearers they are giving u r money back with interest or u can book in oceans... Iam not sure is this a strategy to delay the start up &go with new bookings with a higher price at a later stage.....

Anish Nair
anish nair


16
You can join the owner's group, of Sunteck Signia Orion, Navi Mumbai by clicking on this link http://www.commonfloor.com/signia-orion-navi%20mumbai/povp-xxtt1q and get in touch with other owners who have already booked a flat in this project and discuss about the same.
Commonfloor.com's apartment management software is absolutely free of coast, Anti spam and provides complete data security and privacy(http://www.commonfloor.com/apartment-communities/pricing).
To find the benefits of joining the software please find this link ( http://www.commonfloor.com/apartment-communities/benefits-owners)

Sanjana Jain


17
I have given up on this option , the latest is that the project is being scrapped . I am looking out for other high rise projects , millenium avinash (just behind sunteck oceans) going for a resale flat.. but apparently it does not have OC as of yet as well ... would it make sense to invest in a flat which does not have a OC
Girish


Hi Girish, Its better to have an OC in place. if the Builder is not able to get an OC then there would have been some non-compliance by the Builder in respect to the construction. If the OC is not in place then your basic amentities such as Water from NMMC/BMC gets hampered.

Ranjita
25th February 2014


18
I have also booked flat in Signia Orion and getting similar evasive resposnes from the company. Can we meet builder jointly in one of teh days and get the facts. My contact is 98 21028581
Ajit Manke
Ajit Manke


19
Today when I spoke i got the same reply and they are saying that they are filing case against regulators and the project may get deyaled infinite. It seems builder is not interested to start work as the prices of nearby locations have gone up including Airoli. They (mgmt team) are expected to write to all investors about the same by this weekend.
gahlot_vikram


20
Dear all, we need to take up this matter with Sunteck group's Managing Director. I am getting different responses from different officals of Piramal Sunteck. One is saying IOD is not required while other one is saying they have applied for IOD, one senior official told me that they have applied for NMMC clearance which is required for Environment Clearance while another person is saying they are going to apply for such clearance in a week. We should also send a letter to Piramal group as many customers would have booked flats in this project because of "Piramal" name as developer.
Pramod


21
I agree with you Amit, the way these guys are responding to procedural requirements.. seems they are just not good enough to get things done faster out of govt dept.... projects which were launched latter to this has started work... and these guys are still just figuring out "How to get the permission".... I am surprised how come they have good names like Piramal and Kotak associated with them...
gahlot_vikram


22
I booked in Dec 2011, probably in the 1st 25 people to book. Its more than 2 years and still absurd replies. I think those guys are really lethargic. Getting work out from goverment needs a lot of constant followups, but seems these guys arent pushing. They just get dates after dates and not sure if there paperwork is complete either ! I think we know a considerable number of people. We should form a group and schedule a meeting with someone senior in the firm. Also if I find tonite, I will create a new facebook group so that anyone else wants to join us can also. - Amit
Amit Mishra


23
Hi friends,
Developer will going to apply for the IOD this month end. IOD along with other recommended document will required to present to committee member for approval of environment clearance.
It will take another 6~8 months from now for commencement of work as informed by unofficial personnel.
ravindra


24
HI Rajeev, Guess its gonna take another 4-5 months the way they are responding towards this.. CIDCO may also charge builder interest coz project is delayed (rather will be) beyond the timeline which is 4yrs from purchase of land and its been already 3yrs..
gahlot_vikram


25
The minutes of 23 rd ec meeting mentions that they would consider after builder gets IOD and also they need to get high rise clearance from NMMC. Not sure how much more delay this implies
Rajeev Radhakrishnan


26
Would like to join the group on Whatsapp . I had booked in jan 12. Apparently they have been asked for further clarifications after the 23 dec environment clearance meeting. My no is 9892192725
Rajeev Radhakrishnan


27
Hi friends,

Please read the following, the comments of sunteck customer.

Builder with no Delivery plans
By: clayfern | Jul 29, 2013 05:48 PM

Sunteck Realty Limited - Mumbai

Its 7 years since the project is be developed, and is awarded the project of the year by Accomodations times, however there is no sight of possession.

Infact this is one of builder in mumbai not delivered a single project

Signature Island (BKC)- 2006

Signia Isles - 2009

Signia Pearl - 2010

Signia Oceans - 2009

Signia Orion - 2011

Sunteck City (Goregaon) - 2011
ravindra


28
It is surprising that such a reputed group do not have any process of keeping customers informed about developments. I have not received any written reply to various letters/mails. I have booked flat considering one JV partner is reputed and big business group like Piramal.
Pramod


29
Hi friends,
64th SEIAA meeting minutes will be uploaded by next week.
We will wait and observe if any approval/rejection comments from committee member so that developer can apply for .CC and IOD.
ravindra


30
Hello Friends - wish you all a Very Happy New Year. I have written two letters and numerous e mails to the senior / concerned officials of this developer. I have not received any written reply. I had personal meeting and conversation on telecon about the delay in commencement of construction work of this project. Reply is they are awaiting for approvals. They are saying authorities have cleared project for environment clearance in a meeting held on 23rd Dec 2013 and now only IOD and CC which are pending to start the project work.
Pramod


The moef clearance has not come through. There are still some points which they need to respond after the 23rd december meeting. Then there is highrise issue....and then iod or cc. So.....till then keep following up.
Ashokchauhan, Apartment Resident, Mumbai
5th January 2014


31
Hi Friends, does anyone has any update of 23rd Dec SEIAA meeting?
gahlot_vikram


32
Thanks Vikram point well made ..
Girish


33
Thanks Ravindra for the call and the detailed chat , i will be extra cautious before investing in this project
Girish


34
Hi Girish, May be you can wait and watch for a month or so as there are some developments expected soon. If they are in favour then you can then book the apartment.
gahlot_vikram


35
Dear Girish,

I advice you not to book in Signia Orion due to pending approvals from various authorities.If U are getting discounted rate and willing to wait for next five years, then you can think in booking this project.Otherwise you can go for ready to move property in this area with reliable developer.
Presently they may be selling on words that project will get approvals in short duration.
Do not get trap as we got. We are waiting since last 2 years.
ravindra


36
Am intrested in a 2 BHK flat , apparently all 2 BHK flats in oceans seem to be fully sold off and they have offered me orion instead. It is strange that inspite of all issues they still seem to be selling orion flats to buyers am keen to follow developments on this ..my cordinates 9920051166
Girish


37
Add me too. I booked the flat in Feb 2012. Here are my coordinates 9833115088 - Puneet Mumbai
Puneet Thakur


38
Booked a flat in Feb-2012, please add me to the Whats App group. My number is +0044 7891827234. Archana
Archana Ramakrishnan


39
Booked in Feb 2012. they give me same link and same clarifications as posted above. I spoke to their sales person , he said expected date is mid February...which I don't trust , since that's the way he has been given dates . I am reachable on 9820973607.

Ashok -Thane
Ashokchauhan


40
Hi Pramod and Vikram,

I have also booked the flat in Signia Orion in FEB 2012 . After enquiring with them they told me that they are awaiting the High rise committee approvals and after getting approval they will apply for CC and IOD this means another 6~8 months. Also they has appointed new architecture .Most probably they will commence work in August 2014 expected possession is 2019..
My number is 9930178215 if I am presence in India. Other cell no is 9820784831.
ravindra


41
Correct link

https://ec.maharashtra.gov.in/files/microsoftwordpending_seiaa.pdd
gahlot_vikram


https://ec.maharashtra.gov.in/files/microsoftwordpending_seiaa.pdf
7th December 2013


42
Hi Pramod,

I agree with you as I am based in Dubai i keep talking with one of their senior person with whom I had a detailed discussion last week, however he has shared the following link regarding seiaa meeting expected to happen this month (by 15th Dec) and after this they will apply for IOD/CC which means another 2-3mths. Their name is right up at 1st place link for which is as follows :

https://ec.maharashtra.gov.in/files/microsoftwordpending.seiaa.pdf

If you happen to meet please share your views as well.

PS - Suggestion, can we have everyone's no so that we can make a whats app grp so that we can share info on development / update. My no +971526991323.
gahlot_vikram


43
I have booked a flat in Dec 2011 in this project (Signia Orion). There is no proper and official reply from developer about the commencement of work. Whoever has booked flat in this project should collectively go and meet senior person of this company. My mobile number - 96198 83225
Pramod


44
They got Environmental clearance and permission upto 23 floor.Now they have applied for CC and IOD which may came around first week of january. if during this period LS Election if some problem happen then U have to wait till July 2014 to start the work.and It seen that builder also not interested to starting thr project..As there is no buyer for Signia Oceans because the rate they kept for same is Rs,9000 and for Signia Orion they are quoting Rs.10000 which are very v ery high.
Kindly share more information if u know anything more.
ravindra


45
Hi Ravindra, why what happened to the builder?
gahlot_vikram


46
Don;t book property with this developers.
ravindra


47
Hi Ashok, at last their name is appearing in March-13 agenda list of Env Clearances.. Hopefully they should get permission soon.. A ray of hope :)
gahlot_vikram


It will take another 6~8 months from now to get CC,IOD amd most important environmental clearance
ravindra,  Thane
4th June 2013


Hi Ravindra, they claim that their architect has been arrested due to whatever reason and they now have to start process all over.
22nd June 2013


So yes 6-8month looks very likely..
22nd June 2013


Hi Vikram do u have any news when CC & IOD going to be received
ravindra,  Thane
20th November 2013


48
Ask them first if they have all clearances ( CC etc..) from local bodies to start construction. I am caught since March 2012. No idea when the construction will start!!!!!!!!!
Ashokchauhan


Thanks Ashok, i am visiting them this weekend. BTW what rates did you book at
Girish ,  Mumbai
13th May 2013


Did you book in Orion ? What did they say regarding construction start for this project?? My recommendation would be to book only after they have all permisions /IOD/CC ...else wait.
Ashokchauhan, Apartment Resident, Mumbai
15th May 2013


Dear Ashok do you book flat in Signia Orion.
ravindra,  Thane
17th October 2013


49
I am intrested in this project as it is quite close to my kido's school the asking rate is 9000 sq.ft which is high in that area
Girish


correct rate will be approx.7000 in that area.
ravindra,  Thane
4th June 2013


50
Hi Mr. Ashok recently heard that they have got the CRZ permission and hopefully by month end should get IOD...
gahlot_vikram


Thanks Vikram. I was just updated by their CRM team , when i contacted them. Thanks.
Ashokchauhan, Apartment Resident, Mumbai
18th January 2013


51
I have not booked a flat but I am looking for a flat for investment purpose. So I want to know whether there is any legal issues with the project?
Abhishek


I have booked a flat here since Feb 2012..but since then all evasive replies by the developer regarding the commencement of work. They are not giving any offical reply regarding anything. The delay is already almost a year. Really dont know what is the issue with this.
Ashokchauhan, Apartment Resident, Mumbai
30th December 2012


Hi Mr. Ashok what rates did you get during the pre launch stage
Girish ,  Mumbai
23rd April 2013


Can you please contact me on mobile 96198 83225. I have booked a flat in this project in Dec 2011. I am doing lot of follow up for this project but not getting proper reply. We together can approach this company.
Pramod,  Mumbai
6th December 2013


52
What is the reason the project did not get necessary approval?
Abhishek


Have you booked a flat here Abhishek?
Ashokchauhan, Apartment Resident, Mumbai
24th December 2012


53

Ask a Question
120 Characters Left