Delay in Casa Rio Riverview

Q: Booked a flat in casa Rio Riverview. It was committed to be deliveerd in end 2014. Now, they are saying Jan, 2016!! Anyone else booked anywhere in casa...let's connect. This can't go on. Heard many stories of people not getting possession on time at Casa Rio

Reply

Replies (4)
1
Guys i'm forming a group to fight against Lodha Builders.. I had booked a flat in CASA Rio and the project is delayed for more than 2 years.. I'm about to start a fight for my due compensation.. If you want to join in drop an email with your contact details on belsonkoshy at gmail dot com. Remember we can create a huge impact if our number is large..
belson koshy


Hi,
You can join the Commonfloor Group, of Lodha Casa Rio, Dombivali East by clicking on this link https://www.commonfloor.com/lodha-casa-rio-mumbai/covp-dz5t66 and http://groups.commonfloor.com/ and get in touch with other owners who have already booked a flat in this project and discuss about the same.
Commonfloor.com's apartment management software is absolutely free of cost, Anti spam and provides complete data security and privacy(http://www.commonfloor.com/apartment-communities/pricing).
To find the benefits of joining the software please find this link ( http://www.commonfloor.com/apartment-communities/benefits-owners)
Already 1 lakh apartment society are using Commonfloor Groups to bridge the gap of communication among the owners and MC ( Management Committee)

(http://businesswireindia.com/news/news-details/commonfloorcom-launches-commonfloor-groups/38909 )
13th October 2015


Hi Belson,
You can send a legal notice to the developer mentioning the issues being faced and the relief you seek. Legal notice needs to framed carefully as it is the backbone of any civil or recovery proceeding. If you still don't get any positive reply file a case in the consumer redressal forum for deficiency in service along with the copy of notice.
14th October 2015


2
Hi, Booked a flat in Casa Rio Nyasia. It was committed to be delivered in January 2013..But still waiting for possession... I lost my faith for any future investment with Lodha ....
Dinesh jangid


3
Yes Vatsa, you are right. There are around 150 towers or so in the entire project. However, there are delays in the commitment for a particular phase. And then it means financial losses if the commitment in timelines changes by 2 years! This will also have a cascading effect on the other phases. When we put our money into a project, we should also be on top of things. For a middle-class genuine buyer like myself, it is our life's savings and a huge compromise due to expenses of EMI interests, plus the extended period of staying on rent!!! It actually becomes unmanageable financially. A reputed builder like Lodha should ideally, ensure that their middle-class genuine buyers do not suffer financial losses by investing in their projects.
Samir Kumar


4
Hi Samir, as per my knowledge this project is constructed in phase manner and each and every phase have different possession date.
Vatsa Suman


5