Construction link payment plan of this project is like:-
At the time of registration- 2.25 lac-3.25 lac including service tax ,
Within 60 days- 20% of BSP,
On allotment - 10% of BSP+Floor PLC,
Casting of ground floor roof - 10% of BSP,
Casting of first floor roof- 10% of BSP,
Casting of second floor roof - 10% of BSP+50% of additional cost,
Casting of third floor roof- 10% of BSP,
Casting of 4th floor roof- 10% of BSP+50% of additional cost,
Completion of External plaster- 7.5% of BSP,
Completion of flooring- 7.5% of BSP,
On offer of possession- 5% of BSP+IFMS+Lease rent+EDC & IDC+other chages( if any).