Q:Hi,I booked a flat in Antriksh Golf Link around a year back in tower H.As per the broker this tower was supposed to be the premium tower of all but till now there is no sign of construction of this tower.I have visited the site 3-4 times but everytime builder is giving me excuses though in the agreement it is mentioned that the possession will be given in Dec 2016 which seems next to impossible.so anybody has got information when the construction will be started for Tower H?
Q:Hi all,I am Sapan, booked a 2BHK unit in G Tower of this project....top floor of this tower was completed in jan-2015 and Builder is asking to give possession in 2016 december. But as i am seeing the consturuction progress in the property sites this is still going on .......is any one having actuall update what is going on...or can we get the possession in end of 2016.....???
Latest Answer: I have visited the site, and spoken to the builder. Status is not seeing good. December 16 is next to imposible for possession. But builder is saying for G Tower they will give possession in end of 2016. is anyone who is also purchased house in the same tower G.