Thanx for the update Sanjay. I guess i have not been there for a while now. will do so soon. Are you satisfied with the internal finishing and fixtures provided? have they given wooden flooring in bedrooms and Air-cons as promised?
tanker bore well water comes , this water is passed through water softner plant and pumped up to the overhead tanks . The water TDS is 55 which is better than muncipal water . There is no problem at all . Infact D and E block has 6 families staying in each . Totally D E F @ 11 families .
I think you have not visited this place since long . Yo need to visit
Ignis possession is delayed that is correct and it will come along with D and E , but why they are not allowing you inside the buiding ....difficult to underatand ??? . Yes they may not allow you inside your flat becuase you have yet to take possession .
For your information I am already staying in Ignis F
Hi Sanjay. my flat is also in Ignis F. How r u managing to stay there without the OC? do u get regular drinking water and are the other amenities usable? are the flats finished properly as per their promise?
Any update on Ignis F possession and OC??? everytime i call them they say OC will be issued in 15 days? They are not allowing me to even go inside the building! is anyone planning to take legal action against the builder for all the delay?
I recently visit my flat (Ignis E). Wings D, E & F are complete. Wing A & B look 6 months away. Wing C looks one year away. Lodha expects handover of keys from Jan ’13 – they are waiting for temporary water connection (a mystery as they say OC is in process and going to take six months) Good News – Flat construction quality seems good. Passage road was under construction. Noise issue due to ongoing construction activity was not that bad due to acoustics of large open area. Disappointing News: Cluster clubhouse area is quite small for 450 odd flats. Swimming pool is a bad joke – it’s basically a 10x10 feet pit. Btw, I don’t care for the clubhouse .. this has been a painful journey – just waiting to get rightful possession..
The customer service people are not giving a straight answer regarding the possession date and also regarding the status and progress of the project. Does anyone have a clearer picture?
I recently visit my flat (Ignis E). Wings D, E & F are complete. Wing A & B look 6 months away. Wing C looks one year away. Lodha expects handover of keys from Jan ’13 – they are waiting for temporary water connection (a mystery as they say OC is in process and going to take six months) Good News – Flat construction quality seems good. Passage road was under construction. Noise issue due to ongoing construction activity was not that bad due to acoustics of large open area. Disappointing News: Cluster clubhouse area is quite small for 450 odd flats. Swimming pool is a bad joke – it’s basically a 10x10 feet pit. Btw, I don’t care for the clubhouse .. this has been a painful journey – just waiting to get rightful possession..
I understand possession for fit out is currently on hold and they are not handing over keys to anyone till some global issue related to TMC ( i think also related to OC ) is resolved . I would be happy if someove gives some more update on this regarding timelines