When will the Parinee Almog project Possession available

Q: I have booked 2 units of 2BHK in Parinee Almog pre-launch in 2012 and after 4 years of hibernation still waiting to see if the works starts. Though I have not cancelled the units neither I have applied for it. Can someone genuinely share the reason for such a long delay ...... None of Builder official are sharing the true status nor the timelines or any commitments....
Replies (3)
1
Share your own insights thoughts on the project with all other prospective buyers. Visit propsurf
Rohit


2
Hi Anubhav,
Even i have searched on few realty portals and found that most of the websites have mentioned the possession date December'18.
According to me, it will take another 2 - 3 years from here to offer possession, if the real estate market picks up and they are able to sell the flats.
Dev Patel


3
Hi Anubhav!!
The Wing-A has come up to plinth level and the Wing-B foundation has been done. They did not get the environmental clearance and hence the construction was stopped. This July'14 they got it however they still needed the Construction Certificate to re-start. I was told in Sep that the construction will start in October End I passed by a couple of days ago and still seems no movement. I don't know when they will start the construction.
Dayananda


HI Dayananda,
I had booked a flat in Adney Parinee Almog in 2014 and would like to about the project developments. I spoke to the builder directly and they say it will be ready by September 2017 but from the work that is done up till now it does not look like that they will hand over before 2-3 years. Anyone who has invested or has knowledge about the project do share some information.
18th January 2017