Q:I have booked flat in Himalaya Tanishq, Flat no Z-4 and was promised that the possession will be given in Jan 2016. In aug 2016 they asked to come and take possession but the completion certificate was not available. After that everytime they said that will be done in a month or 2. In Jan 2018 they asked for remaining money but did not mentioned about possession, when asked that whether flat is ready for possession. office personnel, Mr. Harish misbehaves and threatens.
Latest Answer: Did you inform your state RERA? I will suggest you to all buyers of this project to collectively take legal steps against this builder. Your State RERA will help you to get your money back. And the builder has to pay the fine along with interest.