Latest Answer: Hi Mr Mirza,
Installment linked payment plan of this project is like:-
Application money with application form- As applicable,
Within 30days from date of allotment letter- 20% less application money,
Within 60 days - 10%,
On laying of foundation/plinth - 10%,
On laying of ground floor foundation-10%,
On laying of sanitary & piping- 15%,
On completion of internal plaster- 15%,
On completion of external plaster- 15%,
On offer of possession- 5% , + IFMD+ Maintenance Charges+ Social club charges.