Latest Answer: This is in reference of Flat NO 102 of DPWHO PROJECT NO-25 D being Constructed at Dwarka Sector-23B Pocket-:7 POCHANPUR, NEW DELHI. This was booked on 6th September2014 and was to be handed over within 18 months. But Construction never started for this project and after approaching DPW multiple times DPW dodged and were giving fake promises. Due to frustration finally I cancelled project on 26 Feb 2016 because of Their fake promises and Project never started. I am still waiting for payment along with interest which they were supposed to pay on 10th of this month as promised and mentioned in letter. I want DPW response for the same otherwise I have to go for Legal Action against Them as I have given them enough chances and have been waiting for long.
Q:The Tower is now open for possession but the cell phone does not function at all in the upper floors of the tower. The Builder is silent on this issue.
Latest Answer: Hi,
for more information about this project you can click on Bellevue Avenue, Ghaziabad
OR
Kindly call on the toll free number (1800) (180) (180) (180) Or You can Post your Requirements to get matching properties details on your Email and Mobile.
Latest Answer: Angel Jupiter won't be able to start work for new towers. Since, there is a dispute and recently GDA placed their own board on the land - one could see it.
For another tower, angel completed its work till 24 floors and likely to get completed soon - but again no surety - As its Uttar pradesh / Ghaziabad where corruption is in the blood now..
Q:The Builder has 13 blocks for 3 BHK and only 4 has started at the pace he will take all money from us in next 1 year but the handover will be in 3 years
Latest Answer: I dont see any such issue as the axis bank is releasing money on construction linked plan and construction is going on as per demand letter, I have booked in tower zade, regds sandeep sood m 9971489842
Latest Answer: Antariksh Sanskriti project at NH-24 Indirapuram is delayed by 2 years and no sign of completion. Builder has collected 80-90 %payment in most cases and is earning interest on our money. He is not deploying funds sufficient to complete the project. Wish God give him some sense. He talks very nice things in media but does not deliver. We as buyers feel cheated. Investor Clinic was marketing the project. They also do not take any intrest once it is sold. Be aware.
Latest Answer: Its an complete commercial project as per my understanding and there are both type of units: Self Use and Rented one. Company plans to give the entire premises to facility management company (might be big five star or such company) and then provide the profit to the individuals who have invested over there. As of now monthly maintenance part is not clear.