Open Forum about Lodha Casa Univis, Thane
[ Ready to Move In ]Ghodbunder Road, Thane West, Thane - 400607, Maharashtra, INDIA.
Lodha Casa Univis, Thane
[ Ready to Move In ]
Ghodbunder Road, Thane West, Thane - 400607, Maharashtra, INDIA.
Post your requirement
APARTMENTs
30 BLOCKS , 31 FLOORSPrice:
52.33L to
1.27Cr
Unit Details:
500 to 1000 units
1, 2, 3 BHK
639 - 1557 SQFT
1, 2, 3 BHK
639 - 1557 SQFT
Locality:
Builder:
Possession:
Ready to move since Nov 2013
Featured property Agents in the locality

Project Last Updated on : 9 Dec 2016
Lodha Casa Univis Public Forum
Q: I have booked flat in Tiera B. I have a doubt on completion of project by April '13. Does any one know the delay. There is no communication from Builder. The builder is very prompt in asking money but very slow in providing status.

Q: Stalled construction of CASE Univis Cielo C building. If it is due to TMC not providing the permit, what is it that the builder has violated that has compelled the TMC take such action? Is there a way to find out what is the real reason with TMC directly and also whether there is any legal way out builder can take corrective action to resolve the problem? This way we will know whether the building construction is stopped for ever or not.

Also see discussions for
Q: For Casa Univis (or is it now Splendora?) Egnis E, I once again got a call urging me to take Fitout possession. They are not offering any information on OC and consequently the final possession except to say that they have applied for it. But they are trying to get more money out of me by offering fitout possession. Also, on CAM they are saying that it will start from Jan 15, 2013. When I don't have possession of the flat how can they expect me to pay for maintaining it? Also, they have not addressed the issue of doubling the maintenance charges from what was agreed upon. Also, when I asked them if the clubhouse, pool and other infrastructure is ready, they haven't answered in the affirmative. These, by the way, are what this maintenance charge is supposed to be going towards. So, basically Lodha expects the buyer to pay for maintaining infrastructure that isn't ready yet and that the buyer doesn't legally have a right to use.

Q: Hi. What is the latest update on the possession of IGNIS-F at casa univis? has anyone taken possession/paid maintenance?

Q: Hi i have booked 3bhk flat in casa rio, i have pain 80% of payment and due to some unavoidable circumstance there will be some delay from my side in paying balance 20% of cost, i am ready to pay delay payment penalty 18% also, i just want to know what is the maximum time frame lodha can grant to me before they initiate cancellation procedure.

Also see discussions for
Q: Hi All,
I contacted Lodha today and was informed by Vivek Koshti that the possession date for Ceilo C is going to be further postponed to May 2014. They will be sending the letters/email to all the customer next week. This is due to not getting approvals from TMC.
They also informed that they are not planning to pay any compensation/interest payment for the delayed possession as the reason for delay is beyond builders control.
I booked the flat in 2009 and have been paying the interest on loan to bank for last 2 years. I am not comfortable to continue paying further cost for Lodha not managing the project efficiently. I am planning to seek legal options for what can be done in this scenario apart from going to consumer court. I will appreciate if you guys can let me know if you have received any communications from Lodha on this and if you are planning to take any legal action.
Thanks
I contacted Lodha today and was informed by Vivek Koshti that the possession date for Ceilo C is going to be further postponed to May 2014. They will be sending the letters/email to all the customer next week. This is due to not getting approvals from TMC.
They also informed that they are not planning to pay any compensation/interest payment for the delayed possession as the reason for delay is beyond builders control.
I booked the flat in 2009 and have been paying the interest on loan to bank for last 2 years. I am not comfortable to continue paying further cost for Lodha not managing the project efficiently. I am planning to seek legal options for what can be done in this scenario apart from going to consumer court. I will appreciate if you guys can let me know if you have received any communications from Lodha on this and if you are planning to take any legal action.
Thanks

Also see discussions for
Q: How many people have taken fitout possession? Is there any information about it?
The builder is saying that OC will come in about 6-8 months. What is the point to taking fitout possession other than paying the builder the full amount?
Why is the builder charging CAM from 31st, October? My understanding is that as long as the builder doesn't given possession (full possession where I can live in the building) they have possession of the property and therefore any maintenance is their responsibility. How can this be transferred to the buyer without giving possession?
Why is the builder charging CAM from 31st, October? My understanding is that as long as the builder doesn't given possession (full possession where I can live in the building) they have possession of the property and therefore any maintenance is their responsibility. How can this be transferred to the buyer without giving possession?

Q: Guys as you all must be knowing that our project has been delayed by more than 2 years. In my each meeting and written communication with LODHA 'bout the compensation for the delay possession, I was getting replay that that will be adjusted during the possession demand letter. But now last week when I asked my customer representative for a site visit, she asked me to pay the remaining 5% of the consideration i.e. nothing but the possession amount else I won't be allowed for a site visit. And she also confirmed LODHA is in no mood to pay the compensation to us for the delay payment. I asked her that by saying this they are breaching the contract mentioned in the Sale agreement. They said they don't bother 'bout this. So guys I've decided not to pay the possession amount and go to the consumer court. I also think you all will get the same response when you'll be aksing for the compensation. Guys please share your experience and opinion.

Also see discussions for
Q: I have booked a flat in Ignis 'F'. According to the agreement the builder is liable to pay interest on delayed possession after Dec 2011. When I spoke to the customer service person, he told me there is a clause (24) in the agreement which says if any payment is delayed from the buyers side, the builders interest on delayed possession will get forfeited. I have already paid interest on one delayed payment. Can the builder still not pay penalty on delayed possession?

Also see discussions for
Q: My name is Varsha, I have bought a flat in Tiera "A" wing in Sept 2009 and registered in the same month. Till today the construction has reached only the 11th floor and is awaiting permissions. Plz shed some light on the real causes of such a big delay. Also I have received a letter from Lodha about 5% VAT and it is to be paid within 15 days of the receipt of the letter or else it will attract some additional interest. Although we registered in Sept 2009 but had made very little payments until march 2010 (after which the VAT was slashed to 1%). Do we still have to pay the 5% VAT or should it be charged as and how the construction progresses? (like the service tax)