Q:1) I booked flat in CASA UNIVIS (Now CASA Splendora) TEIRRA- C 1802 in Aug'2009. 2) With the assurance of possession in March'2012 Sale agreement also prepared. However till date possession is not in place. 3) Every now and then their sales executive informed me new possession dates and now almost more than 2 years of delay there is no confirmation on possession date. 4) In line with agreement I have paid entire amount against builders demand letter. However at this stage, in spite of delay from builder side builder is not giving me compensation calculated @ rate of 12% per annum on the amount paid by me (part of agreement). 5) Builder informed me that this delay in completion project is, due to labour problem, getting CC is beyond their control and he is not responsible to pay for that. This argument is not at all acceptable as this is prime responsibility of any builder to take care such issues. 6) I am currently staying nearby locality on rental basis and paying heavily as a rent, in addition to it I am paying heavy EMI.7) I want builder to give me compensation and handover flat as per the current confirmation i.e. Sep'2014
Q:Stalled construction of CASE Univis Cielo C building. If it is due to TMC not providing the permit, what is it that the builder has violated that has compelled the TMC take such action? Is there a way to find out what is the real reason with TMC directly and also whether there is any legal way out builder can take corrective action to resolve the problem? This way we will know whether the building construction is stopped for ever or not.
Latest Answer: i guess we need to talk to each other and stay in touch and fight this nuisance as a team. Individually neither the builder nor the Thane registration Dept will entertain us. My name is Roshan Fernandes and my mobile no is 9004467787. i am on watsapp too. we can start a community and get together and approach them as a group. please dont take it lightly, its bcos of our carefree nature these people get away with things.