ajayd, Mumbai
Q: When is the possession of the Oasis project happening? Dec 2012 was the date as per the developer while selling of the flats. No communication has from the developers yet
My replies to this discussion
I too have booked a flat here. The CC approval for wing B has not yet received due to which construction is stopped. CC is not received from BMC since environment clearance of the project is pending. This info I got ffrom my last communication with Srishti office.I too have booked a flat here. The CC approval for wing B has not yet received due to which construction is stopped. CC is not received from BMC since environment clearance of the project is pending. This info I got ffrom my last communication with Srishti office.
Hi ...On proptiger website the expected completion date is Nov 2015 for this project. We need to speak sternly with builder on this.Hi ...On proptiger website the expected completion date is Nov 2015 for this project. We need to speak sternly with builder on this.
My comments to replies
I too have booked a flat here. The CC approval for wing B has not yet received due to which construction is stopped. CC is not received from BMC since environment clearance of the project is pending. This info I got ffrom my last communication with Srishti office.
Any further updates on this ?
18th May 2013
Thanks Vaibhav.. Sent u the details on ur email id.
19th May 2013