Q: I had booked a flat at casa rio viva (d) in 2010 and project kicked off 0n 2011, as per their commitments it was going to be positioned in 2012, which never happened and moreover they dont entertain people to see their building, very sluggish answers from represntatives. now they had given me a new date of May 14, and i know again they are going to shift. above all we are suffering from other burdens.
My replies to this discussion
Dear Zulfi, I am also in the same position, booked in Casa rio in 2010 and builder has again postponed date to April 15. My one close relative also want to buy one, but after seeing this response of builder he quits his decision. Why builder doesn't understand of customer problems... This will making down their own reputation. Regards akgDear Zulfi, I am also in the same position, booked in Casa rio in 2010 and builder has again postponed date to April 15. My one close relative also want to buy one, but after seeing this response of builder he quits his decision. Why builder doesn't understand of customer problems... This will making down their own reputation. Regards akg
Thanks god, Finally, I got a fit-out letter from Lodha in last week, The final payment is have to do till Diwali. So, its around 2.75 years late... Regards, akg, ThaneThanks god, Finally, I got a fit-out letter from Lodha in last week, The final payment is have to do till Diwali. So, its around 2.75 years late... Regards, akg, Thane
Dear Zulfi, I am also in the same position, booked in Casa rio in 2010 and builder has given me next new date Aug 14. I think this will again be postponed. RegardsDear Zulfi, I am also in the same position, booked in Casa rio in 2010 and builder has given me next new date Aug 14. I think this will again be postponed. Regards
Ask a Question
120 Characters Left





    Trending Categories

    CommonFloor Property Search Mobile App now available on Android, iOS and Windows!