guys note pls as per commonfloor it is completed in march 2015. this is wrong..very slow progress at site..lots of issues with builder misleading customer..poor construction quality,agreements in favor of builder..etc and looks at this rate 1 year work remaining..hope project final handover will be 2016 and it will be good news for us cheated buyersguys note pls as per commonfloor it is completed in march 2015. this is wrong..very slow progress at site..lots of issues with builder misleading customer..poor construction quality,agreements in favor of builder..etc and looks at this rate 1 year work remaining..hope project final handover will be 2016 and it will be good news for us cheated buyers
My comments to replies
It's been under construction since Oct 2011. Many commitments lapses on completion dates. First commitment was Oct2013...Second was Feb14...last one was Oct14 for A-block only & even that is been missed out. There is really no care taker within Century on commitment ownership. B & C blocks are faar off from the reality for completion on revised commitment of Dec14!!!
true.century just cheat customers. for a small project they take so much time. I wonder how many decades taking for bigger project like ethos they r launching.i was taking few customers and they are complaining that work is very slow of saras. customers fed up
18th April 2015

Q: Can anyone one please help me out with some information about the project?

My replies to this discussion
This 6 month completion time mentioned I keep hearing about century Saras from mid 2013 , but not happening. Builder not delivering as per timelines . Good time to invest in north Bangalore though !!This 6 month completion time mentioned I keep hearing about century Saras from mid 2013 , but not happening. Builder not delivering as per timelines . Good time to invest in north Bangalore though !!
My comments to replies
Ongoing base price is INR 3500/sq-ft. Only 3bhk available and that too hardly 10-15 units.
Hi Dixit, dont buy with century. this project they say is another 2 years to ready.lot of people have been duped to buy in the name of holy swamijis to buy and we r regretting....very much delay
30th June 2014
Heard century retaining terraces in this project apart from new construction against rules.Owning or occupying the terrace of a housing society building is unfair and illegal. The builder/developer has no right to sell the terrace. Some developers of co-operative housing societies resort to the unfair practice of selling the rooftop / terrace. It has also come to light that in some housing societies, owners of the flats at the top floor claim ownership of the terrace and dissuade other owners from using the same. Both these actions are contrary to the stipulations as per law. According to Section 4 (1A), (iii), (viii), (x) and Section 10(1) of Maharashtra Ownership Flats Act, 1963, the builder/developer has no right to sell the terrace. The builder also does not have the authority to sell the terrace of a building. As per law, all open spaces in a building, including the terrace is a common easement for the benefit of all the members who are entitled to enjoy . Vinayak, Bangalore
3rd April 2015