Dear Friends
You know me as coordinator to NSSWO (a JNU Society) for IRIDIA project at sector 86 Noida. I am also one of the allotee in the project and am effected by the ongoing issues between the Noida Authority and builder of the project.
In the view of ongoing issue we feel that you all are clueless and in a state of confusion, therefore, some of us have decided to meet for the following
1. To form a Buyers Welfare Association/Group to represent all buyers in the project
2. To formulate our strategy during this period of crises: i) How to involve ourselves in the process of court hearing as at the end of the day we are who are being effected the most
ii) How to make the Bank consider this period as Zero Period for us and restrain it to disburse any further payment to the builder as well as does not mention this as default on our part.(on cibil etc)
3. To formulate a strategy to safeguard our hard earned money etc
These are only few points of discussions. AnyDear Friends
You know me as coordinator to NSSWO (a JNU Society) for IRIDIA project at sector 86 Noida. I am also one of the allotee in the project and am effected by the ongoing issues between the Noida Authority and builder of the project.
In the view of ongoing issue we feel that you all are clueless and in a state of confusion, therefore, some of us have decided to meet for the following
1. To form a Buyers Welfare Association/Group to represent all buyers in the project
2. To formulate our strategy during this period of crises: i) How to involve ourselves in the process of court hearing as at the end of the day we are who are being effected the most
ii) How to make the Bank consider this period as Zero Period for us and restrain it to disburse any further payment to the builder as well as does not mention this as default on our part.(on cibil etc)
3. To formulate a strategy to safeguard our hard earned money etc
These are only few points of discussions. Any
Dear Friends
You know me as coordinator to NSSWO (a JNU Society) for IRIDIA project at sector 86 Noida. I am also one of the allotee in the project and am effected by the ongoing issues between the Noida Authority and builder of the project.
In the view of ongoing issue we feel that you all are clueless and in a state of confusion, therefore, some of us have decided to meet for the following
1. To form a Buyers Welfare Association/Group to represent all buyers in the project
2. To formulate our strategy during this period of crises: i) How to involve ourselves in the process of court hearing as at the end of the day we are who are being effected the most
ii) How to make the Bank consider this period as Zero Period for us and restrain it to disburse any further payment to the builder as well as does not mention this as default on our part.(on cibil etc)
3. To formulate a strategy to safeguard our hard earned money etc
These are only few points of discussions. AnyDear Friends
You know me as coordinator to NSSWO (a JNU Society) for IRIDIA project at sector 86 Noida. I am also one of the allotee in the project and am effected by the ongoing issues between the Noida Authority and builder of the project.
In the view of ongoing issue we feel that you all are clueless and in a state of confusion, therefore, some of us have decided to meet for the following
1. To form a Buyers Welfare Association/Group to represent all buyers in the project
2. To formulate our strategy during this period of crises: i) How to involve ourselves in the process of court hearing as at the end of the day we are who are being effected the most
ii) How to make the Bank consider this period as Zero Period for us and restrain it to disburse any further payment to the builder as well as does not mention this as default on our part.(on cibil etc)
3. To formulate a strategy to safeguard our hard earned money etc
These are only few points of discussions. Any
My comments to replies
Dear Friends
You know me as coordinator to NSSWO (a JNU Society) for IRIDIA project at sector 86 Noida. I am also one of the allotee in the project and am effected by the ongoing issues between the Noida Authority and builder of the project.
In the view of ongoing issue we feel that you all are clueless and in a state of confusion, therefore, some of us have decided to meet for the following
1. To form a Buyers Welfare Association/Group to represent all buyers in the project
2. To formulate our strategy during this period of crises: i) How to involve ourselves in the process of court hearing as at the end of the day we are who are being effected the most
ii) How to make the Bank consider this period as Zero Period for us and restrain it to disburse any further payment to the builder as well as does not mention this as default on our part.(on cibil etc)
3. To formulate a strategy to safeguard our hard earned money etc
These are only few points of discussions. Any
Dear Sir,
I am Advocate Vaibhav Mahajan, Delhi High Court, and have represented many clients successfully against Ekdant Builders by lodging FIR against them, in past to get their refund back.
Presently i have 2-3 clients wanting refund in Horizon Iridia. I am looking for more such people to make a group.
If you have not received your refund kindly contact
Please provide me ur email id and contact to form a group of iridia buyers Gaurav 9910646464 garysachdeva@gmail.com
12th September 2016
this project has been stopped. Noida Authority has declined the approval & the construction has been stoped. thos who have invest in this project pls share your number or email id
Please provide me ur email id and contact to form a group of iridia buyers Gaurav 9910646464 garysachdeva@gmail.com
12th September 2016
You are right. IRIDA Project in Sec 86, has been stopped. I visited site on 14th Jan 2015 and there is no further construction on it. Noida Authority has stopped construction. We need to make a group for compensation and refund on money.
Please provide me ur email id and contact to form a group of iridia buyers Gaurav 9910646464 garysachdeva@gmail.com
12th September 2016
Hi Sasmita,
As per my knowledge , this project has been stopped. Noida Authority has declined the approval & the construction has been stooped. So those who have invested on this project , they will get their money with interest as per court order. So if any one planning to invest on this project kindly wait & contact previous house owners or investors for latest information.
Please provide me ur email id and contact to form a group of iridia buyers Gaurav 9910646464 garysachdeva@gmail.com
12th September 2016
i have invested in 3+1 (1500 sqft) 1 year back but this project construction is stopped from last 1 month. i visited recently (January 4th, 2014).
is there any more people who has already invested?
we all investors should take an action. what you other investors taking action.
Please provide me ur email id and contact to form a group of iridia buyers Gaurav 9910646464 garysachdeva@gmail.com
12th September 2016
Hello all investors, you please write your email id or contact me on my email at [infoamitmishra@yahoo.com] we need to take a legal action to get our money back or flats delivered.
we need you support.
Please provide me ur contact or call to form a group of iridia buyers Gaurav 9910646464 garysachdeva@gmail.com