Heena Tickoo Wali
Q: Hi, I have booked a 2BHK in Mantri Serene A wing, wanted to know hows everything looking there, by what time we can get possession, any problems with water supply or anything. Please suggest.

My replies to this discussion
We purchased Mantri serene flat A-908 in August 2013 and were assured that the final delivery would be offered by dec or max jan 2014.. Accordingly we aligned our finances with respect to rent and EMIs. Moreover, 85% payment was demanded in dec 2013, stating that project is delayed by a few months. With that in consideration we were told and we believed that delivery would happen max by mar-apr 2014 The next demand letter for 90% payment was dated August 2014. Since we were already following up with Mantri sales team for final date of possession and were not getting any clear updates from them, I kept telling them that anymore payments only when I got clarity on final delivery.. But they did not give us any timelines and instead they blackmailes us that they would charge us interest on that if not paid. We eventually succumbed and made teh payment. In dec 2014, they asked for 100% payment for softt possession and upon asking final date again blackmailed us with charging interesWe purchased Mantri serene flat A-908 in August 2013 and were assured that the final delivery would be offered by dec or max jan 2014.. Accordingly we aligned our finances with respect to rent and EMIs. Moreover, 85% payment was demanded in dec 2013, stating that project is delayed by a few months. With that in consideration we were told and we believed that delivery would happen max by mar-apr 2014 The next demand letter for 90% payment was dated August 2014. Since we were already following up with Mantri sales team for final date of possession and were not getting any clear updates from them, I kept telling them that anymore payments only when I got clarity on final delivery.. But they did not give us any timelines and instead they blackmailes us that they would charge us interest on that if not paid. We eventually succumbed and made teh payment. In dec 2014, they asked for 100% payment for softt possession and upon asking final date again blackmailed us with charging interes
Mantri Realty buyers, please get iin touch with us on 9619500072 so we can screw their happiness togetherMantri Realty buyers, please get iin touch with us on 9619500072 so we can screw their happiness together
My comments to replies
It is February 2015 and the work is still not complete in Mantri Serene. Possession was promised in Dec 2013. The sales office keeps on committing deadlines and failing on them.
We purchased Mantri serene flat A-908 in August 2013 and were assured that the final delivery would be offered by dec or max jan 2014.. Accordingly we aligned our finances with respect to rent and EMIs. Moreover, 85% payment was demanded in dec 2013, stating that project is delayed by a few months. With that in consideration we were told and we believed that delivery would happen max by mar-apr 2014 The next demand letter for 90% payment was dated August 2014. Since we were already following up with Mantri sales team for final date of possession and were not getting any clear updates from them, I kept telling them that anymore payments only when I got clarity on final delivery.. But they did not give us any timelines and instead they blackmailes us that they would charge us interest on that if not paid. We eventually succumbed and made teh payment. In dec 2014, they asked for 100% payment for softt possession and upon asking final date again blackmailed us with charging interes
26th March 2015
Mansi, you can find me on Facebook under the same name. Lets connect pls
26th March 2015

Ask a Question