Q: Can anybody confirm the actual status on site? Why they are not asking for slab wise installments?

My replies to this discussion
Hi Vipul, I have visited the site 2 weeks back and inquired the same. They have told that all the Mumbai side buildings are still awaiting some approvals therefore, it will take 3 more months for starting construction. It is said that podium level is completed for the entire construction area, including 30+ buildings as well. Which floor you are in 34?Hi Vipul, I have visited the site 2 weeks back and inquired the same. They have told that all the Mumbai side buildings are still awaiting some approvals therefore, it will take 3 more months for starting construction. It is said that podium level is completed for the entire construction area, including 30+ buildings as well. Which floor you are in 34?