Q: I have booked a flat in LDA srishti apartment flat Kursi rd scheme 3 years back. Can any one please tell me what is the status of project. LDA people even do not pick the phone.

My replies to this discussion
Its quite a good place. All kind of city bus and shared auto is available. Mall is just 1 KM from there. Good market place at tedhi pulia 2.5 KM I think from our apartment which has a big market. Appreciation depend on demand not amenities, other wise crowd-est places in city did not get appreciated where no basic amenities are available. Flat culture itself is new to lucknow, most of the people buy land instead of resale flat, this situation is changing very rapidly because land cost gone high and people who's parents etc only live, are preferring flats because of safety and services. by current trend, had our flat completed today, it's cost would have been any where between 40 to 45 lacs.Its quite a good place. All kind of city bus and shared auto is available. Mall is just 1 KM from there. Good market place at tedhi pulia 2.5 KM I think from our apartment which has a big market. Appreciation depend on demand not amenities, other wise crowd-est places in city did not get appreciated where no basic amenities are available. Flat culture itself is new to lucknow, most of the people buy land instead of resale flat, this situation is changing very rapidly because land cost gone high and people who's parents etc only live, are preferring flats because of safety and services. by current trend, had our flat completed today, it's cost would have been any where between 40 to 45 lacs.
What can we expect from gov sponsored schemes, esp UP gov. In name of poor and farmers, the goons of gov had taken a free ride.What can we expect from gov sponsored schemes, esp UP gov. In name of poor and farmers, the goons of gov had taken a free ride.
I have already paid all the amounts. But had I knew that they are going to work like this, I would not have paid the deposit. I argue that you should not pay the money unless 75% work will not be done.I have already paid all the amounts. But had I knew that they are going to work like this, I would not have paid the deposit. I argue that you should not pay the money unless 75% work will not be done.
Utter Hopelessness, My relative went today at Srishti and Engineer said that nothing is in his hand, what ever LDA decides, we do, and I do not foresee anything materializing any time soon.Utter Hopelessness, My relative went today at Srishti and Engineer said that nothing is in his hand, what ever LDA decides, we do, and I do not foresee anything materializing any time soon.
ROFL, LDA again gave advertisement for Sargam apartment registration, after Srishti and Smiriti, it is again a doom to project of LDA. We should spared awareness so that our near and dear do not get tangled in this schemes.ROFL, LDA again gave advertisement for Sargam apartment registration, after Srishti and Smiriti, it is again a doom to project of LDA. We should spared awareness so that our near and dear do not get tangled in this schemes.
Dear All, following are the details which My Brother in Law received in written, now add + 6 month at max in this optimistically Srishti Aprtment will be delivered and opened for registration in the month of january 2015.Dear All, following are the details which My Brother in Law received in written, now add + 6 month at max in this optimistically Srishti Aprtment will be delivered and opened for registration in the month of january 2015.
What a shame on Akhilesh Gov. Using farmers to shield it's greed and Goonism. Utter disgust.What a shame on Akhilesh Gov. Using farmers to shield it's greed and Goonism. Utter disgust.
I recently visited, it is not going to finish every thing in less than 1.5 years.I recently visited, it is not going to finish every thing in less than 1.5 years.
I visited Srishti site yesterday and following is my conclusion: 1. Accountant said registration may happen optimistically in sep-oct 2015 for D,E and F buildings. A,B,C and G,H,I will take more time. 2. Engineer told me that, and I saw also, D,E,F are in their final stage of finishing, that includes tiles work, finishing, painting, doors and electric fitting, plumbing. Engineer said, registration may happen but to complete these work it will take 5-6 month for D,E,F. Same is my observation too. After that LDA will clean up the path for D,E,F and make livable in 2-3 months. So by next march april 2016, D,E,F will be in livable situation. For Srishti rest of the blocks - Livable by sep-oct 2016 For Smriti------- Livable by april - may 2017. Work is going in full swing. Nearby area is well developed now.I visited Srishti site yesterday and following is my conclusion: 1. Accountant said registration may happen optimistically in sep-oct 2015 for D,E and F buildings. A,B,C and G,H,I will take more time. 2. Engineer told me that, and I saw also, D,E,F are in their final stage of finishing, that includes tiles work, finishing, painting, doors and electric fitting, plumbing. Engineer said, registration may happen but to complete these work it will take 5-6 month for D,E,F. Same is my observation too. After that LDA will clean up the path for D,E,F and make livable in 2-3 months. So by next march april 2016, D,E,F will be in livable situation. For Srishti rest of the blocks - Livable by sep-oct 2016 For Smriti------- Livable by april - may 2017. Work is going in full swing. Nearby area is well developed now.
They have build 4 blocks, 1 block is completely remaining in 13 floor building. But, other lower floor blocks, not much work is done. and they will not handover few blocks, unless completed all the blocks. LDA people are saying this december, but that is highly unlikely. We will not get possession before next diwali.They have build 4 blocks, 1 block is completely remaining in 13 floor building. But, other lower floor blocks, not much work is done. and they will not handover few blocks, unless completed all the blocks. LDA people are saying this december, but that is highly unlikely. We will not get possession before next diwali.
See, problem is with unprofessional approach and excessive political interfere. My Aunty works in LDA. One day 5000 people mob came and did not allowed any one to exit from LDA premise over compensation issue. These goons have done it twice. Third time they called Police force. Its not a bad investment, just that we have paid all the money. That we should not have paid. now same flat is selling arounf 40-45 lac with that amount of extra lands around buildings.See, problem is with unprofessional approach and excessive political interfere. My Aunty works in LDA. One day 5000 people mob came and did not allowed any one to exit from LDA premise over compensation issue. These goons have done it twice. Third time they called Police force. Its not a bad investment, just that we have paid all the money. That we should not have paid. now same flat is selling arounf 40-45 lac with that amount of extra lands around buildings.
Dear All, LDA officials are not giving reply mail after mail. Mail is a valid way of communication for RTI. Please take following Email IDs and ask for details, delivery, and monetary remuneration for delaying the project. This is following letter written by My relative to LDA repetitively. But no reply. Please write emails asking the detail. PLEASE SHARE your CONTACT DETAILS TOO. NO BODY IN THIS OPEN WORLD IS GOING TO MISUSE IT. rakesht.tripathi@gmail.com From: avdhesh shukla To: contact lda ; "ldapro@yahoo.com" Sent: Friday, 18 December 2015 5:11 PM Subject: Fw: Registration of 401-D BLOCK, SHRISHTI APARTMENT, SITAPUR ROAD SCHEME, SECTOR J, JANAKIPURAM LUCKNOW Dear Sir / Madam Kind attention to Vice Chairman and Secretary Apropos my earlier mails and your reply dated February 25, 2015 (copy attached). Sincerely request you to update me about the status of the captioned project.Dear All, LDA officials are not giving reply mail after mail. Mail is a valid way of communication for RTI. Please take following Email IDs and ask for details, delivery, and monetary remuneration for delaying the project. This is following letter written by My relative to LDA repetitively. But no reply. Please write emails asking the detail. PLEASE SHARE your CONTACT DETAILS TOO. NO BODY IN THIS OPEN WORLD IS GOING TO MISUSE IT. rakesht.tripathi@gmail.com From: avdhesh shukla To: contact lda ; "ldapro@yahoo.com" Sent: Friday, 18 December 2015 5:11 PM Subject: Fw: Registration of 401-D BLOCK, SHRISHTI APARTMENT, SITAPUR ROAD SCHEME, SECTOR J, JANAKIPURAM LUCKNOW Dear Sir / Madam Kind attention to Vice Chairman and Secretary Apropos my earlier mails and your reply dated February 25, 2015 (copy attached). Sincerely request you to update me about the status of the captioned project.
LDA Ashok Pal is the concern person. His mobile no is 9918001701. Every one please call this fellow on regular basis and get the status. His supervisor's name and no is following: N.N. Singh 09335201046LDA Ashok Pal is the concern person. His mobile no is 9918001701. Every one please call this fellow on regular basis and get the status. His supervisor's name and no is following: N.N. Singh 09335201046
Continuing my last comment, Following are the steps: 1. Keep writing weekly mail to LDA official about status, and remuneration for delayed project. 2. We will write emails to Chief minister and secretary also. These two activities for next 2 months. 3. After that a simple case can be filed based on letters, emails etc. Any other suggestions welcomed.Continuing my last comment, Following are the steps: 1. Keep writing weekly mail to LDA official about status, and remuneration for delayed project. 2. We will write emails to Chief minister and secretary also. These two activities for next 2 months. 3. After that a simple case can be filed based on letters, emails etc. Any other suggestions welcomed.
My comments to replies
Would pl any body let me now the details of consumer forum in Lucknow? I would be going to consumer court under the act mentioned by parul saxena. 3 years passed but ground work is yet to begun for Sulabh? Anybody willing to join me for going to consumer forum for compensation for the delay?
Include me too. My email id is rakesht.tripathi@gmail.com. Please mail me, and we will discuss.
2nd August 2013
LDA Ashok Pal is the concern person. His mobile no is 9918001701. Every one please call this fellow on regular basis and get the status.
2nd August 2013

Me too a shristi apartment buyer , How can I join this group ...please let me know
I do not think that its a group, its only a discussion tag. You can ask any question directly here or share information if you have any.
16th July 2014

I and my Cousin booked two flats, one in Gomtinagar and another at Kanpur road under Sulabh Awas Yojna. We found out from the LDA office somewhere in March and they said that the work at Kanpur road was complete and they will star the registration in the first week of April. But soon after that when I phoned to find out, they said Abhi Kahan. It will take time. can any one find out what is going on? Why LDA is not trying to solve the problem. All of us have paid the full amount and till now there is no solution since we booked in 2010.
I have no Idea about sulabh awas, but Srishti, smriti and Sargam, apartment are too delayed, and hopefully we can get in 1 year.
16th July 2014

Dear Everyone, Girija is correct. I have visited the site and it will be going to take 08-12 months. Deepak Srivastava
That was my assessment also when I visited the site in Mid Feb. It will take at least March 2015 for any formal registration process.
2nd June 2014

Can anybody update me on the progress of Smriti apartments?
Yea, As per my visit in Feb 2014, I guessed that we will possession in diwali 2015.
15th August 2014

Please go though the link below for more info on Compensation clauses.... http://www.hindustantimes.com/India-news/NewDelhi/Demand-compensation-from-builders-for-construction-delays/Article1-777593.aspx "The Supreme Court (SC), in the landmark judgement in the case of Lucknow Development Authority vs MK Gupta, made it clear that “when possession of property is not delivered within the stipulated period, the delay so caused is denial of service” and a consumer who is a victim of such delay is entitled to compensation."
LDA Ashok Pal is the concern person. His mobile no is 9918001701. Every one please call this fellow on regular basis and get the status.
2nd August 2013

Any response from LDA on registration? please add me to any discussion forums on same rastogidevarshi@gmail.com
I called LDA few days back and found that only cleaning work is pending. I did not visit but from LDA officials. So they are opening tender for site cleaning. Hopefully before march 2017 we can get possession.
1st September 2016

I visited Apartment site on 21st & it will take at least one year to get completed possession by dec -16
It's really disappointing. As per my assessment in May 2015, I was expecting DEF delivery by March -April 2016, and rest of the block by Oct 2016. So even after 7 months same evaluation is done. +3 month. I tried to contact LDA engineers and accountant, no body is picking phone. Very frustrating situation. However, I am visiting in Feb-March 2016 and based on evaluation I am going to file a law suite against LDA. So who ever want to support me, please extend your email id and contact details so that we can form a group. Thanks Rakesh
13th December 2015

Dear rakesh LDA never give the possession before the next election bcz LDA has no money in his AC which was taken for to develop the apartment .when BSP govt .came again than it will furnished and its true so wait and watch and we have only right to wait and nothing .
I visited Srishti site yesterday and following is my conclusion: 1. Accountant said registration may happen optimistically in sep-oct 2015 for D,E and F buildings. A,B,C and G,H,I will take more time. 2. Engineer told me that, and I saw also, D,E,F are in their final stage of finishing, that includes tiles work, finishing, painting, doors and electric fitting, plumbing. Engineer said, registration may happen but to complete these work it will take 5-6 month for D,E,F. Same is my observation too. After that LDA will clean up the path for D,E,F and make livable in 2-3 months. So by next march april 2016, D,E,F will be in livable situation. For Srishti rest of the blocks - Livable by sep-oct 2016 For Smriti------- Livable by april - may 2017. Work is going in full swing. Nearby area is well developed now.
10th May 2015

Hello all I have been following this discussion occasionally, not witnessing much progress as of yet. I am one of the owners currently out of Lucknow, due to visit the construction site in April 2015 and also enquire about its status at LDA personally. Is anyone interested in legal action against LDA on this matter, should there be no reasonable progress till my visit? Please bear in mind that my time and resources are as valuable as yours, so no time wasters, and clearly this will need funding. Please reply here - and I will chase up emails, phones etc of the interested parties. Cheers pixelface (apologies for the alias - too fussy about privacy !!) pixelface, Lucknow 13th February 2015
I got a reply from LDA officials today that registration process will start in May... fingers crossed!!
18th February 2015
I visited Srishti site yesterday and following is my conclusion: 1. Accountant said registration may happen optimistically in sep-oct 2015 for D,E and F buildings. A,B,C and G,H,I will take more time. 2. Engineer told me that, and I saw also, D,E,F are in their final stage of finishing, that includes tiles work, finishing, painting, doors and electric fitting, plumbing. Engineer said, registration may happen but to complete these work it will take 5-6 month for D,E,F. Same is my observation too. After that LDA will clean up the path for D,E,F and make livable in 2-3 months. So by next march april 2016, D,E,F will be in livable situation. For Srishti rest of the blocks - Livable by sep-oct 2016 For Smriti------- Livable by april - may 2017. Work is going in full swing. Nearby area is well developed now.
10th May 2015

Hi, LDA started constructing Shrishti Apartment Yojna in 2009 which comprised 520 flats. Even after 5 years, the flats have not been completed. While structures of few blocks have been erected, other blocks have not been even half completed. The finishing work is all left. Also, basic facilities are missing here.
Like the law and order, like the business deals!!! No professionalism, all farce.
28th July 2014

Happy new year all of you ....any updates on srishti apartments since it is jan 2015 now .
I got a reply from LDA officials today that registration process will start in May this year ... fingers crossed!!
18th February 2015

I have been alloted a flat at Smriti Apartment, Jankipuram Extension, Lucknow by LDA on 2011. I came to know that the construction of the flat is stopped. Can anyone help me in getting the information about the same.
LDA Ashok Pal is the concern person. His mobile no is 9918001701. Every one please call this fellow on regular basis and get the status.
2nd August 2013

Dear All, following are the details which My Brother in Law received in written, now add + 6 month at max in this optimistically Srishti Aprtment will be delivered and opened for registration in the month of january 2015.
They have written the delivery date as Jan 2015. I add 3-4 month more, else I am going to file a case against LDA. We can make an owner's association in gmail. I will form a forum on gmail and share the link here.
5th November 2014

If you are the owner or resident of apartment then you can join the owners group of the same and discuss with other owners/residents of the project in the group. To join click Owners Group.
We must join this group
2nd August 2013

"LDA Lucknow to launch master plan for 2031" This is the news. I wonder how can they launch new plans if they are unable to clear their previous pending schemes. And why and how can public trust these new schemes? LDA should clear all the back lot before they launch any new scheme. I mean they should not be allowed to do so. This is just a discussion and we are helpless. And I think all of us in this forum are facing the same problem. Can anyone suggest any solution? Betel, Nainital
Actually If this had been a private builder, its easy to go to law reinforcement agencies, problem comes when government go into business! by all means government will protect itself. If if we get ruling in our favor, every one know that how difficult it is to get your money back! Who will protect from protector.....
28th July 2014

i am also asking the same question
LDA Ashok Pal is the concern person. His mobile no is 9918001701. Every one please call this fellow on regular basis and get the status.
2nd August 2013

I visited Srishti site yesterday and following is my conclusion: 1. Accountant said registration may happen optimistically in sep-oct 2015 for D,E and F buildings. A,B,C and G,H,I will take more time. 2. Engineer told me that, and I saw also, D,E,F are in their final stage of finishing, that includes tiles work, finishing, painting, doors and electric fitting, plumbing. Engineer said, registration may happen but to complete these work it will take 5-6 month for D,E,F. Same is my observation too. After that LDA will clean up the path for D,E,F and make livable in 2-3 months. So by next march april 2016, D,E,F will be in livable situation. For Srishti rest of the blocks - Livable by sep-oct 2016 For Smriti------- Livable by april - may 2017. Work is going in full swing. Nearby area is well developed now.
I wish if I could upload some snaps too, but that is not possible with comment it seems! Yes it is too delayed, and no justification can explain LDA's lethargy. Because of that my mother has to live in rented house. But there are some solace in form of construction quality, huge open space, wide kursi road in front of apartment, well developed market at tedhi pulia which is 2 Km from our apartment, and I feel good connectivity in term of city bus and shared auto.
17th May 2015
No Sandhya, I also do not have Status update. But it is confirmed that all the work is done.
15th November 2015

I booked a flat in smriti appartments, can anybody please update on latest developments Fahad, baroda
Minimum 1 year.
5th July 2014

Dear All, Any update on Smriti Apartments?
Dear All, following are the details which My Brother in Law received in written, now add + 6 month in this optimistically Srishti Aprtment will be delivered and opened for registration in the month of january 2015.
29th September 2014

Continuing my last comment, Following are the steps: 1. Keep writing weekly mail to LDA official about status, and remuneration for delayed project. 2. We will write emails to Chief minister and secretary also. These two activities for next 2 months. 3. After that a simple case can be filed based on letters, emails etc. Any other suggestions welcomed.
Thanks guys. Keep writing mails as many authorities as you can. Automated reply is coming from following email id contactuslda22@gmail.com Following automated reply I get: Thank You For Contacting Us. Your E-Mail/Request is being forwarded to Concerned Officer for Necessary Action/Reply. We will revert back to you with action taken status at the earliest.
20th December 2015
They are highly corrupt people, morally and ethically as well. I heard that LDA official ask money for registration. Be aware of that trap too!
21st December 2015
Hey Abhishek, Please send snaps on rakesht.tripathi@gmail.com. Thnx
28th December 2015
Thanks Abhishek. your guess of 6 month is good given the ordinary circumstances.
29th December 2015
I am creating a email group. I collected the email IDs available here. Rest of the people can send me email on rakesht.tripathi@gmail.com
13th February 2016
Gazab idiots hain, is salo ko kya fark padta hai ki ghar mile ya na mile, ye kamine to sarkari naukari kar hi rahe hain, Thanks mohit for information. I think, there is no point holding ourself, people in lucknow should start leagl process, We will support financially. Mohit, added you to our gmail group. I request more people to join the group and start exploring legal options.
14th May 2016